PGRR #5 · Revision Request
PGRR005 New Planning Guide Section 4, Transmission Planning Criteria (formerly "New Planning Guide Section 5, Planning Criteria")
ReasonThe proposed language currently exists in Section 4, Planning, of the Nodal Operating Guides that contains specific policies and requirements that are directly related to transmission planning of the ERCOT System and thus are appropriate for inclusion in the new Planning Guide. The Planning Guide is being developed as requested by the Reliability and Operations Subcommittee (ROS) and the Technical Advisory Committee (TAC).
Created2011-02-25
Approved2011-08-16
Sections Affected
44.14.24.2.14.2.1.14.2.1.24.34.3.14.3.2 (All New)
Summary
This Planning Guide Revision Request (PGRR) adds new Section 4, Planning Criteria to the Planning Guide.
Action Log 7 milestones
-
Feb 25
PLWGDeferred/Tabled→ PLWG Language Consideration
-
Mar 25
PLWGDeferred/Tabled→ PLWG Consideration
-
Apr 29
PLWGRecommended for Approval→ PLWG IA Review
-
May 26
PLWGRecommended for Approval→ ROS Consideration
-
Jun 16
ROSRecommended for Approval→ TAC for consideration.
-
Jul 7
TACRecommended for Approval→ ERCOT Board Consideration
-
Aug 16
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Apr 29 '11 | PLWG | Consensus to recommend approval of PGRR005 as revised by PLWG | |
| May 26 '11 | PLWG | Consensus to endorse and forward the 4/29/11 PLWG Report as amended by the 5/20/11 ERCOT comments and as revised by PLWG and the Impact Analysis for PGRR005 to ROS | |
| Jun 16 '11 | ROS | To to recommend approval of PGRR005 as amended by the 6/13/11 CenterPoint Energy comments. | Passed |
| Jul 7 '11 | TAC | To recommend approval of PGRR005 as amended by the 6/30/11 ERCOT comments and as revised by TAC | Passed |
Documents 13
| Name | Type | Posted | Classification |
|---|---|---|---|
| 005PGRR-01 New Planning Guide Section 5 Planning Criteria 011111 | doc | Jan 11 '11 | Revision Request |
| 005PGRR-02 PLWG Report 022511 | doc | Mar 1 '11 | Committee Report |
| 005PGRR-03 PLWG Report 032511 | doc | Mar 30 '11 | Committee Report |
| 005PGRR-04 PLWG Report 042911 | doc | May 4 '11 | Committee Report |
| 005PGRR-05 Impact Analysis 051711 | doc | May 17 '11 | Committee Report |
| 005PGRR-06 ERCOT Comments 052011 | doc | May 20 '11 | Revision Request Comments |
| 005PGRR-07 PLWG Report 052611 | doc | May 31 '11 | Committee Report |
| 005PGRR-08 Luminant Comments 060811 | doc | Jun 14 '11 | Revision Request Comments |
| 005PGRR-09 CenterPoint Energy Comments 061311 | doc | Jun 14 '11 | Revision Request Comments |
| 005PGRR-10 ROS Report 061611 | doc | Jun 20 '11 | Committee Report |
| 005PGRR-11 ERCOT Comments 063011 | doc | Jun 30 '11 | Revision Request Comments |
| 005PGRR-12 TAC Report 070711 | doc | Jul 8 '11 | Committee Report |
| 005PGRR-13 Board Report 081611 | doc | Aug 16 '11 | Committee Report |
Meetings That Took It Up 13
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Nov 28 '11 | Planning Working Group (PLWG) Meeting | PLWG | Concluded |
| Aug 16 '11 | Board of Directors Meeting | BOARD | Concluded |
| Jul 29 '11 | Joint CMWG/PLWG Meeting | PLWG | Concluded |
| Jul 7 '11 | TAC Meeting | TAC | Concluded |
| Jun 16 '11 | ROS Meeting | ROS | Concluded |
| Jun 15 '11 | PLWG Special WebEx Meeting | PLWG | Concluded |
| May 26 '11 | Planning Working Group (PLWG) Meeting | PLWG | Concluded |
| Apr 29 '11 | Planning Working Group Meeting | PLWG | Concluded |
| Apr 18 '11 | Planning Working Group (PLWG) Meeting via WebEx | PLWG | Concluded |
| Mar 25 '11 | Planning Working Group Meeting | PLWG | Concluded |
| Mar 7 '11 | OWG Meeting | OWG | Concluded |
| Feb 25 '11 | Planning Working Group Meeting | PLWG | Concluded |
| Feb 16 '11 | OWG Meeting | OWG | Concluded |