PGRR #4 · Revision Request

PGRR004  Synchronization with NPRR291, Reduce the Comment Period for NPRRs and SCRs

Approved sponsor ERCOT posted 2010-12-27 ercot.com
ReasonAs a result of the Technical Advisory Committee (TAC) structural and process review, TAC requested ERCOT staff to draft an NPRR to reduce the comment period for NPRRs to 14 days. Since PGRRs have a similar initial comment period, proposed revisions to Planning Guide revision process are included in this PGRR to align with the Nodal Protocol revision process.
Created2011-01-21
Approved2011-05-17
Sections Affected
2.4.3
Summary
This Planning Guide Revision Request (PGRR) reduces the comment period for PGRRs from 21 days to 14 days and removes the requirement for the comment period to end at least three Business Days prior to the next regularly scheduled Planning Working Group (PLWG) meeting.
Action Log 5 milestones
Documents 7
NameTypePostedClassification
004PGRR-01 Synchronization with NPRR291, Reduce the Comment Peri doc Dec 27 '10 Revision Request
004PGRR-02 Impact Analysis 122710 doc Dec 27 '10 Staff Report
004PGRR-03 PLWG Report 012111 doc Jan 26 '11 Committee Report
004PGRR-04 PLWG Report 022511 doc Mar 1 '11 Committee Report
004PGRR-05 ROS Report 031011 doc Mar 11 '11 Committee Report
004PGRR-06 TAC Report 040711 doc Apr 12 '11 Committee Report
004PGRR-07 Board Report 051711 doc May 20 '11 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Apr 7 '11 TAC Meeting TAC Concluded
Mar 10 '11 ROS Meeting ROS Concluded
Feb 25 '11 Planning Working Group Meeting PLWG Concluded
Jan 21 '11 Planning Working Group Meeting PLWG Concluded