PGRR #2 · Revision Request

PGRR002  New Planning Guide Section 2, Definitions and Acronyms, and Section 8, Planning Reserve Margin (PRM) and Associated Change Process for the PRM (formerly "New Planning Guide Section 2, Definitions and Acronyms, and Section 8, Planning Reserve Margin")

Approved sponsor PLWG posted 2010-11-12 ercot.com
ReasonCurrently, the definition of the PRM, current minimum PRM planning criterion (13.75%), and methodology necessary to calculate the PRM are not included in the Protocols, Operating Guides or Planning Guide. Because of the market and reliability impacts of the PRM, it is necessary for these items to be included in the Protocols, Operating Guides or Planning Guide. The Planning Working Group (PLWG) recommends that this information be inserted into the ERCOT Planning Guide to ensure visibility to the market and to provide for a structured change process to ensure that any modification to the definition or calculation of the PRM can be fully vetted by Market Participants. A central location for terms and definitions specific to the Planning Guides is needed.
Created2010-12-13
Approved2011-04-19
Sections Affected
2 (new)2.1 (new)2.2 (new)8 (new)8.1 (new)8.2 (new)8.3 (new)8.3.1 (new)8.3.2 (new)
Summary
This Planning Guide Revision Request (PGRR) incorporates the following into the Planning Guide: (1) Planning Reserve Margin (PRM) and the minimum PRM requirement. (2) The methodology to be used by ERCOT to calculate its Seasonal (i.e., Summer and Winter) PRM. This methodology is based on the ERCOT reserve margin calculation methodology developed by the Generation Adequacy Task Force (GATF) and approved by the ERCOT Board in May 2005. (3) Changes in the PRM calculation methodology developed by the GATF and approved by TAC in February 2010. (4) Current ERCOT reserve margin planning criterion of 13.75%. (5) New Section 2 to the Planning Guides which adds relevant terms and definitions used in the Planning Guide not defined in the Protocols. To allow for inclusion of the definitions and acronyms into the Planning Guide as Section 2, the current Section 2, Process for Planning Guide Revision, will be renumbered as Section 1, Process for Planning Guide Revision. (6) Changes in Section 2.1 to incorporate an administrative change process for the PRM.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Dec 13 '10PLWG Consensus to recommend approval of PGRR002 as revised by the PLWG
Feb 18 '11ROS To recommend approval of PGRR002 as revised by the 2/4/11 ERCOT commentsPassed
Documents 9
NameTypePostedClassification
002PGRR-01 New Planning Guide Section 2 Definitions and Acronyms doc Nov 12 '10 Revision Request
002PGRR-02 CEO Revision Request Review 112310 doc Nov 23 '10 Revision Request Comments
002PGRR-03 PLWG Report 121310 doc Dec 16 '10 Committee Report
002PGRR-04 Impact Analysis 122710 doc Dec 27 '10 Staff Report
002PGRR-05 PLWG Report 012111 doc Jan 26 '11 Committee Report
002PGRR-06 ERCOT Comments 020411 doc Feb 4 '11 Revision Request Comments
002PGRR-07 ROS Report 021811 doc Feb 22 '11 Committee Report
002PGRR-08 TAC Report 030311 doc Mar 4 '11 Committee Report
002PGRR-09 Board Report 041911 doc Apr 21 '11 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Apr 19 '11 Board of Directors Meeting BOARD Concluded
Mar 3 '11 TAC Meeting TAC Concluded
Feb 18 '11 ROS Meeting ROS Concluded
Jan 21 '11 Planning Working Group Meeting PLWG Concluded
Dec 13 '10 Planning Working Group Meeting PLWG Concluded
Nov 30 '10 Planning Working Group Meeting PLWG Concluded