OBDRR #10 · Revision Request
OBDRR010 Related to NPRR910, Clarify Treatment of RUC Resource that has a Day-Ahead Market Three-Part Supply Award
ReasonAddresses current operational issues
Created2019-01-30
Approved2019-02-12
Sections Affected
Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder
Summary
This Other Binding Document Revision Request (OBDRR) codifies that for a Resource that has been Awarded a Three-Part Supply Offer in the Day-Ahead Market (DAM) but decides not to operate the Resource in the Real-Time Market (RTM) and subsequently receives a Reliability Unit Commitment (RUC) instruction to operate, that Resource’s High Sustained Limit (HSL) will continue to be included in the On-Line capacity considered in Operating Reserve Demand Curve (ORDC) pricing.
Action Log 2 milestones
-
Jan 30
TACRecommended for Approval→ Board for consideration
-
Feb 12
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Jan 30 '19 | TAC | To recommend approval of OBDRR010 as amended by the 1/22/19 ERCOT comments as revised by TAC | Passed |
Documents 5
| Name | Type | Posted | Classification |
|---|---|---|---|
| 010OBDRR-01 Related to NPRR910, Clarify Treatment of RUC Resource that has a Day Ahead Market Three Party Supply Award 112818 | doc | Nov 28 '18 | Revision Request |
| 010OBDRR-02 Impact Analysis 112818 | doc | Nov 28 '18 | Staff Report |
| 010OBDRR-03 ERCOT Comments 012219 | doc | Jan 22 '19 | Revision Request Comments |
| 010OBDRR-04 TAC Report 013019 | doc | Feb 1 '19 | Committee Report |
| 010OBDRR-05 Board Report 021219 | doc | Feb 13 '19 | Committee Report |
Meetings That Took It Up 2
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Feb 12 '19 | Board of Directors Meeting | BOARD | Concluded |
| Jan 30 '19 | TAC Meeting | TAC | Concluded |