OBDRR #4 · Revision Request
OBDRR004 Updates to Emergency Response Service Procurement Methodology
ReasonMarket efficiencies or enhancements
Created2018-05-24
Approved2018-06-12
Sections Affected
Emergency Response Service Procurement Methodology
Summary
This Other Binding Document Revision Request (OBDRR) revises the risk-weighting factors available for ERCOT to assign to each ERS Time Period in Section E, ERS Expenditure Limit; describes the process for updating the ERS Time Period Expenditure Limits for any subsequent Standard Contract Terms if money is needed to fund and ERS renewal Contract Period; and updates Table A in Section F, Capacity Inflection Point, to reflect the proposed changes to the risk-weighting factors.
Action Log 2 milestones
-
May 24
TACRecommended for Approval→ Board for consideration
-
Jun 12
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| May 24 '18 | TAC | To endorse OBDRR004 as amended by the 4/18/18 ERCOT comments and the associated Impact Analysis with a proposed effective date of July 1, 2018 | Passed |
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 004OBDRR-01 Updates to Emergency Response Service Procurement Methodology 040318 | docx | Apr 3 '18 | Revision Request |
| 004OBDRR-02 Impact Analysis 040318 | docx | Apr 3 '18 | Staff Report |
| 004OBDRR-03 ERCOT Steel Mills Comments 040918 | docx | Apr 9 '18 | Revision Request Comments |
| 004OBDRR-04 ERCOT Comments 041818 | docx | Apr 18 '18 | Revision Request Comments |
| 004OBDRR-05 TAC Report 052418 | docx | May 24 '18 | Committee Report |
| 004OBDRR-06 Board Report 061218 | docx | Jun 12 '18 | Committee Report |
Meetings That Took It Up 2
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 12 '18 | Board of Directors Meeting | BOARD | Concluded |
| May 24 '18 | TAC Meeting | TAC | Concluded |