NPRR #980 · Revision Request
NPRR980 Accounting for NSO Forced Outages and GINR Inactive Projects in the Report on the Capacity, Demand and Reserves in the ERCOT Region
ReasonMarket efficiencies or enhancements
Created2019-12-12
Approved2020-02-11
Sections Affected
3.2.6.2.23.14.1.1
Summary
This Nodal Protocol Revision Request (NPRR) makes two changes to the Report on the Capacity, Demand and Reserves in the ERCOT Region methodology. First, it clarifies that Forced Outages greater than 180 days, submitted through a Notification of Suspension of Operations (NSO), should be excluded from the Report on the Capacity, Demand and Reserves in the ERCOT Region capacity estimates for the expected duration of the Forced Outages. Currently, such NSO Outages are not addressed in the Report on the Capacity, Demand and Reserves in the ERCOT Region capacity estimation methodology. This NPRR also adds language in Section 3.14.1.1 to clarify that the NSO outage information may be published in the Report on the Capacity, Demand and Reserves in the ERCOT Region. Second, Planning Guide Revision Request (PGRR) 066, Interconnection Request Cancellation and Creation of Inactive Status, which was approved by the ERCOT Board in December 2018, creates a new “Inactive” status for Generation Interconnection and Change Request (GINR) projects. This NPRR addresses the resulting reporting gap by specifying how “Inactive” GINR projects, as well as “Cancelled” projects, are to be treated in the Report on the Capacity, Demand and Reserves in the ERCOT Region.
Action Log 4 milestones
-
Dec 12
PRSRecommended for Approval→ Impact Analysis Consideration
-
Jan 16
PRSRecommended for Approval→ Revision Request Consideration
-
Jan 29
TACRecommended for Approval→ Revision Request Consideration
-
Feb 11
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Dec 12 '19 | PRS | to recommend approval of NPRR980 as amended by the 11/11/19 WMS comments | Passed |
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 980NPRR-01 Accounting for NSO Forced Outages and GINR Inactive Projects in the Report on the Capcity, Demand and Reserves in the ERCOT Region 110519 | docx | Nov 5 '19 | Revision Request |
| 980NPRR-02 Impact Analysis 110519 | docx | Nov 5 '19 | Staff Report |
| 980NPRR-03 WMS Comments 111119 | docx | Nov 11 '19 | Revision Request Comments |
| 980NPRR-04 PRS Report 121219 | docx | Dec 17 '19 | Committee Report |
| 980NPRR-05 PRS Report 011620 | docx | Jan 22 '20 | Committee Report |
| 980NPRR-06 TAC Report 012920 | docx | Jan 31 '20 | Committee Report |
| 980NPRR-07 Board Report 021120 | docx | Feb 14 '20 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Feb 11 '20 | Board of Directors Meeting | BOARD | Concluded |
| Jan 29 '20 | TAC Meeting | TAC | Concluded |
| Jan 16 '20 | PRS Meeting | PRS | Concluded |
| Dec 12 '19 | PRS Meeting | PRS | Concluded |
| Nov 6 '19 | WMS Meeting | WMS | Concluded |