NPRR #958 · Revision Request
NPRR958 Modifications to Wind and Solar Capacity Calculations in the CDR
- PRS Sep 12 '19
- TAC Sep 25 '19
- BOARD Oct 8 '19
- PUCT —
ReasonMarket efficiencies or enhancements
Created2019-08-15
Approved2019-10-08
Sections Affected
3.2.6.2.2
Summary
This Nodal Protocol Revision Request (NPRR) modifies the calculation of the wind and solar capacities used in the Report on Capacity, Demand and Reserves in the ERCOT Region (CDR). It also better aligns the solar capacity calculation with the wind capacity calculation.
Timeline
- Jul 19
-
Aug 15
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR958 as submitted” — Passed→ Impact Analysis Consideration
-
Sep 12
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 8/15/19 PRS Report and Impact Analysis for NPRR958” — Passed→ Revision Request Consideration
-
Sep 25
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR958 as recommended by PRS in the 9/12/19 PRS Report” — Passed→ Revision Request Consideration
-
Oct 8
BOARD Board of Directors MeetingBOARDApproved“to approve NPRR958 as recommended by TAC in the 9/25/19 TAC Report” — Passed
-
—