NPRR #929 · Revision Request
NPRR929 PTP Obligations with Links to an Option DAM Award Eligibility
- PRS May 9 '19
- TAC May 22 '19
- BOARD Jun 11 '19
- PUCT —
ReasonAddresses current operational issues
Created2019-04-11
Approved2019-06-11
Sections Affected
4.4.6.3 (new)
Summary
This Nodal Protocol Revision Request (NPRR) proposes new criteria for determining whether a Point-to-Point (PTP) Obligation with Links to an Option bid is eligible to be awarded based on the Current Operating Plan (COP) Resource Status of the Resource at the Resource Node where the bid sources. Such a bid will not be eligible for award if it sources at a Resource with a COP Resource Status of OUT, or a COP Resource Status of OFF and the Resource is not offered into the Day-Ahead Market (DAM).
Timeline
-
Mar 26
PRSFiled by LCRA, Reliant Energy Retail Services, STEC, Direct Energy, Austin Energy, and CPS Energy
-
Apr 1
Listed without action at 2 meetings (Apr 1 '19 – Apr 3 '19)
-
Apr 11
PRS PRS MeetingPRSRecommended for Approval Amended by the Apr 9 '19 Luminant Generation comments“to recommend approval of NPRR929 as amended by the 4/9/19 Luminant Generation comments” — Passed→ Impact Analysis Consideration
-
May 9
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC priority 2019 · rank 2655“to endorse and forward to TAC the 4/11/19 PRS Report, as revised by PRS, and the Impact Analysis for NPRR929 with a recommended priority of 2019 and a rank of 2655” — Passed→ Revision Request Consideration
-
May 22
TAC TAC MeetingTACRecommended for Approval Amended by the May 15 '19 ERCOT comments“to recommend approval of NPRR929 as recommended by PRS in the 5/9/19 PRS Report as amended by the 5/15/19 ERCOT comments as revised by TAC” — Passed→ Revision Request Consideration
-
Jun 11
BOARD Board of Directors MeetingBOARDApproved“to approve NPRR929 as recommended by TAC in the 5/22/19 TAC Report” — Passed