NPRR #926 · Revision Request

NPRR926  Removal of 90-Day Period Between SSR Study Approval and Synchronization

Approved sponsor ERCOT posted 2019-02-27 ercot.com
ReasonAddresses current operational issues
Created2019-03-14
Approved2019-06-11
Sections Affected
3.22.1.216.5
Summary
This Nodal Protocol Revision Request (NPRR) removes the 90-day period between Subsynchronous Resonance (SSR) study approval and Initial Synchronization specified in paragraph (4) of Section 16.5, Registration of a Resource Entity, clarifies that the SSR Mitigation Plan is part of the SSR study, and adds an ERCOT review process for the SSR study (with any required mitigation plan) including 30 days for the study to be approved by ERCOT. This NPRR also adds a 45 day time period from SSR study approval for ERCOT to implement any required SSR monitoring.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Apr 11 '19PRS to recommend approval of NPRR926 as amended by the 4/8/19 Oncor commentsPassed
May 22 '19TAC to recommend approval of NPRR926 as recommended by PRS in the 5/9/19 PRS Report as revised by TACPassed
Documents 9
NameTypePostedClassification
926NPRR-01 Removal of 90 Day Period Between SSR Study Approval and Sychronization 022719 doc Feb 27 '19 Revision Request
926NPRR-02 Impact Analysis 022719 doc Feb 27 '19 Staff Report
926NPRR-03 PRS Report 031419 doc Mar 15 '19 Committee Report
926NPRR-04 ROS Comments 040519 doc Apr 5 '19 Revision Request Comments
926NPRR-05 Oncor Comments 040819 doc Apr 8 '19 Revision Request Comments
926NPRR-06 PRS Report 041119 doc Apr 15 '19 Committee Report
926NPRR-07 PRS Report 050919 doc May 10 '19 Committee Report
926NPRR-08 TAC Report 052219 doc May 23 '19 Committee Report
926NPRR-09 Board Report 061119 doc Jun 12 '19 Committee Report
Meetings That Took It Up 15
DateMeetingCommitteeStatus
Dec 10 '19 Board of Directors Meeting BOARD Concluded
Nov 20 '19 TAC Meeting TAC Concluded
Nov 7 '19 ROS Meeting ROS Concluded
Oct 3 '19 ROS Meeting ROS Concluded
Sep 18 '19 PLWG Meeting PLWG Concluded
Sep 5 '19 ROS Meeting ROS Concluded
Aug 8 '19 ROS Meeting ROS Concluded
Jul 16 '19 PLWG Meeting PLWG Concluded
Jul 11 '19 ROS Meeting ROS Concluded
Jun 11 '19 Board of Directors Meeting BOARD Concluded
May 22 '19 TAC Meeting TAC Concluded
May 9 '19 PRS Meeting PRS Concluded
Apr 11 '19 PRS Meeting PRS Concluded
Apr 4 '19 ROS Meeting ROS Concluded
Mar 14 '19 PRS Meeting PRS Concluded