NPRR #921 · Revision Request
NPRR921 RTF-2 Elimination of the Terms All-Inclusive Generation Resource and All-Inclusive Resource
ReasonAddresses current operational issues / Market efficiencies or enhancements
Created2019-02-14
Approved2019-06-11
Sections Affected
1.21.6.52.13.2.6.2.23.73.10.13.10.63.10.7.23.10.7.68.1.1.4.28.5.1.18.5.1.28.5.28.5.2.19.17.110.110.2.210.2.310.3.2.410.914.5.116.516.5.1.222L23Iand ERCOT Fee Schedule
Summary
This Nodal Protocol Revision Request (NPRR) proposes clarifications in furtherance of the Resource Definition Task Force’s (RTF) objectives to “identify[] problematic terms” in the Protocols and “improv[e] the current structure and terms where practical.” Specifically, this NPRR replaces all instances of the terms All-Inclusive Generation Resource and All-Inclusive Resource with appropriate terms from Section 2.1. The terms All-Inclusive Generation Resource and All-Inclusive Resource cause confusion because many generators that fall within the scope of the definitions of these terms are neither Generation Resources nor Resources. In most cases, ERCOT has simply replaced the term All-Inclusive Generation Resource with “Generation Resource and Settlement Only Generator (SOG),” and replaced All-Inclusive Resource with “Generation Resource, Settlement Only Generator (SOG), and Load Resource.” However, in many of the cases where All-Inclusive Generation Resource is currently used, ERCOT has determined that the requirement should apply only to certain categories of registered generators and has revised the language appropriately. For example, ERCOT has proposed that Primary Frequency Response should be provided only by Generation Resources and any other transmission-connected generators, and that it need not be provided by distribution-connected generators. In these cases, the elimination of All-Inclusive Generation Resource enables ERCOT to more narrowly tailor the requirement’s applicability to a reasonable scope. In several other instances, ERCOT has supplemented an existing reference to Generation Resource with a reference to SOG, or the appropriate subtype of SOG, to further clarify the requirement’s applicability.
Action Log 5 milestones
-
Feb 14
PRSRecommended for Approval→ PRS for Impact Analysis review
-
Mar 14
PRSRecommended for Approval→ TAC for consideration
-
Mar 27
TACDeferred/Tabled→ TAC for consideration
-
May 22
TACRecommended for Approval→ Board for consideration
-
Jun 11
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Mar 14 '19 | PRS | To endorse and forward to TAC the 2/14/19 PRS Report as amended by the 3/12/19 ERCOT comments as revised by PRS and Impact Analysis for NPRR921 | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 921NPRR-01 RTF-2 Elimination of the Terms All Inclusive Generation Resource and All Inclusive Resource 012819 | doc | Jan 28 '19 | Revision Request |
| 921NPRR-02 Impact Analysis 012819 | doc | Jan 28 '19 | Staff Report |
| 921NPRR-03 PRS Report 021419 | doc | Feb 14 '19 | Committee Report |
| 921NPRR-04 ERCOT Comments 031219 | doc | Mar 12 '19 | Revision Request Comments |
| 921NPRR-05 PRS Report 031419 | doc | Mar 15 '19 | Committee Report |
| 921NPRR-06 TAC Report 032719 | doc | Mar 28 '19 | Committee Report |
| 921NPRR-07 TAC Report 052219 | doc | May 23 '19 | Committee Report |
| 921NPRR-08 Board Report 061119 | doc | Jun 11 '19 | Committee Report |
Meetings That Took It Up 10
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 11 '19 | Board of Directors Meeting | BOARD | Concluded |
| May 22 '19 | TAC Meeting | TAC | Concluded |
| Apr 4 '19 | ROS Meeting | ROS | Concluded |
| Mar 27 '19 | TAC Meeting | TAC | Concluded |
| Mar 26 '19 | MSWG Meeting | MSWG | Concluded |
| Mar 14 '19 | PRS Meeting | PRS | Concluded |
| Mar 14 '19 | RTF Meeting | RTF | Concluded |
| Mar 7 '19 | ROS Meeting | ROS | Concluded |
| Feb 14 '19 | PRS Meeting | PRS | Concluded |
| Feb 14 '19 | RTF Meeting | RTF | Concluded |