ERCOT·WATCH Search ercot.com  ⌕
NPRR #921 · Revision Request

NPRR921  RTF-2 Elimination of the Terms All-Inclusive Generation Resource and All-Inclusive Resource

Approved sponsor ERCOT posted 2019-01-28 ercot.com
ReasonAddresses current operational issues / Market efficiencies or enhancements
Created2019-02-14
Approved2019-06-11
Sections Affected
1.21.6.52.13.2.6.2.23.73.10.13.10.63.10.7.23.10.7.68.1.1.4.28.5.1.18.5.1.28.5.28.5.2.19.17.110.110.2.210.2.310.3.2.410.914.5.116.516.5.1.222L23Iand ERCOT Fee Schedule
Summary
This Nodal Protocol Revision Request (NPRR) proposes clarifications in furtherance of the Resource Definition Task Force’s (RTF) objectives to “identify[] problematic terms” in the Protocols and “improv[e] the current structure and terms where practical.” Specifically, this NPRR replaces all instances of the terms All-Inclusive Generation Resource and All-Inclusive Resource with appropriate terms from Section 2.1. The terms All-Inclusive Generation Resource and All-Inclusive Resource cause confusion because many generators that fall within the scope of the definitions of these terms are neither Generation Resources nor Resources. In most cases, ERCOT has simply replaced the term All-Inclusive Generation Resource with “Generation Resource and Settlement Only Generator (SOG),” and replaced All-Inclusive Resource with “Generation Resource, Settlement Only Generator (SOG), and Load Resource.” However, in many of the cases where All-Inclusive Generation Resource is currently used, ERCOT has determined that the requirement should apply only to certain categories of registered generators and has revised the language appropriately. For example, ERCOT has proposed that Primary Frequency Response should be provided only by Generation Resources and any other transmission-connected generators, and that it need not be provided by distribution-connected generators. In these cases, the elimination of All-Inclusive Generation Resource enables ERCOT to more narrowly tailor the requirement’s applicability to a reasonable scope. In several other instances, ERCOT has supplemented an existing reference to Generation Resource with a reference to SOG, or the appropriate subtype of SOG, to further clarify the requirement’s applicability.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Mar 14 '19PRS To endorse and forward to TAC the 2/14/19 PRS Report as amended by the 3/12/19 ERCOT comments as revised by PRS and Impact Analysis for NPRR921Passed
Documents 8
NameTypePostedClassification
921NPRR-01 RTF-2 Elimination of the Terms All Inclusive Generation Resource and All Inclusive Resource 012819 doc Jan 28 '19 Revision Request
921NPRR-02 Impact Analysis 012819 doc Jan 28 '19 Staff Report
921NPRR-03 PRS Report 021419 doc Feb 14 '19 Committee Report
921NPRR-04 ERCOT Comments 031219 doc Mar 12 '19 Revision Request Comments
921NPRR-05 PRS Report 031419 doc Mar 15 '19 Committee Report
921NPRR-06 TAC Report 032719 doc Mar 28 '19 Committee Report
921NPRR-07 TAC Report 052219 doc May 23 '19 Committee Report
921NPRR-08 Board Report 061119 doc Jun 11 '19 Committee Report
Meetings That Took It Up 10
DateMeetingCommitteeStatus
Jun 11 '19 Board of Directors Meeting BOARD Concluded
May 22 '19 TAC Meeting TAC Concluded
Apr 4 '19 ROS Meeting ROS Concluded
Mar 27 '19 TAC Meeting TAC Concluded
Mar 26 '19 MSWG Meeting MSWG Concluded
Mar 14 '19 PRS Meeting PRS Concluded
Mar 14 '19 RTF Meeting RTF Concluded
Mar 7 '19 ROS Meeting ROS Concluded
Feb 14 '19 PRS Meeting PRS Concluded
Feb 14 '19 RTF Meeting RTF Concluded