NPRR #920 · Revision Request
NPRR920 Change to Ramp Rate Calculation in Resource Limit Calculator
ReasonAddresses current operational issues
Created2019-02-14
Approved2019-04-09
Sections Affected
6.5.7.2
Summary
This Nodal Protocol Revision Request (NPRR) modifies the Resource ramp rate logic in Section 6.5.7.2, Resource Limit Calculator, to dynamically adjust the amount of ramp rate reserved for Regulation Service in Real-Time based on the percentage of Regulation Service being deployed in the opposite direction in Real-Time.
Action Log 4 milestones
-
Feb 14
PRSRecommended for Approval→ Impact Analysis Consideration
-
Mar 14
PRSRecommended for Approval→ Revision Request Consideration
-
Mar 27
TACRecommended for Approval→ Revision Request Consideration
-
Apr 9
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Mar 14 '19 | PRS | to endorse and forward to TAC the 2/14/19 PRS Report as amended by the 3/11/19 ERCOT comments and the Impact Analysis for NPRR920 with a recommended priority of 2019 and rank of 2690 | Passed |
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 920NPRR-01 Change to Ramp Rate Calculation in Resource Limit Calculator 012519 | doc | Jan 25 '19 | Revision Request |
| 920NPRR-02 Impact Analysis 012519 | doc | Jan 25 '19 | Staff Report |
| 920NPRR-03 PRS Report 021419 | doc | Feb 18 '19 | Committee Report |
| 920NPRR-04 ERCOT Comments 031119 | doc | Mar 11 '19 | Revision Request Comments |
| 920NPRR-05 PRS Report 031419 | doc | Mar 15 '19 | Committee Report |
| 920NPRR-06 TAC Report 032719 | doc | Mar 28 '19 | Committee Report |
| 920NPRR-07 Board Report 040919 | doc | Apr 10 '19 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Apr 9 '19 | Board of Directors Meeting | BOARD | Concluded |
| Mar 27 '19 | TAC Meeting | TAC | Concluded |
| Mar 14 '19 | PRS Meeting | PRS | Concluded |
| Feb 14 '19 | PRS Meeting | PRS | Concluded |