NPRR #919 · Revision Request
NPRR919 Exemption from Governor Primary Frequency Response Control for Certain Resources in Private Use Networks
- PRS ✕ rejected Sep 12 '19
- TAC —
- BOARD —
- PUCT —
ReasonMarket efficiencies or enhancements
Created2019-02-14
Rejected2019-09-12
Sections Affected
8.5.1.1
Summary
This Nodal Protocol Revision Request (NPRR) allows a Resource in a Private Use Network whose primary function is providing steam to a host, and is not participating in the ERCOT energy market, to be exempted from Primary Frequency Response service requirements. The Governor will still be in service, but may be allowed to be in pressure control instead of Primary Frequency Response control.
Timeline
-
Jan 18
PRSFiled by Formosa Utility Venture, Ltd
-
Feb 7
Listed without action at 1 meeting
-
Feb 14
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS“to table NPRR919 and refer the issue to ROS” — Passed→ Language Consideration
- Mar 7
- Mar 14
- Apr 4
-
Apr 11
Listed without action at 4 meetings (Apr 11 '19 – Jun 13 '19)
- Jul 11
-
Jul 17
Listed without action at 4 meetings (Jul 17 '19 – Sep 5 '19)
- Sep 12
- Sep 25