NPRR #913 · Revision Request
NPRR913 Generator Interconnection Neutral Project Classification
ReasonMarket efficiencies or enhancements
Created2019-01-17
Rejected2019-04-11
Sections Affected
3.11.4.3
Summary
This Nodal Protocol Revision Request (NPRR) addresses the neutrality of projects required to interconnect generation to the ERCOT Transmission Grid, and projects for the reliable operation of the generation under particular conditions described in North American Electric Reliability Corporation (NERC) Standard TPL-001-4 – Transmission System Planning Performance Requirements.
Action Log 2 milestones
-
Jan 17
PRSDeferred/Tabled→ Language Consideration
-
Apr 11
PRSRejected
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Apr 11 '19 | PRS | to recommend approval of NPRR913 as amended by the 4/5/19 ROS comments | Failed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Apr 11 '19 | PRS | Motion Fails | 3.4 | 3.6 | 0 | xls |
| Apr 11 '19 | PRS | Motion Fails | 3.4 | 3.6 | 2 | xls |
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 913NPRR-01 Generator Interconnection Neutral Project Classification 120718 | doc | Dec 7 '18 | Revision Request |
| 913NPRR-02 PRS Report 011719 | doc | Jan 21 '19 | Committee Report |
| 913NPRR-03 ROS Comments 020819 | doc | Feb 8 '19 | Revision Request Comments |
| 913NPRR-04 ROS Comments 040519 | doc | Apr 5 '19 | Revision Request Comments |
| 913NPRR-05 PRS Report 041119 | doc | Apr 16 '19 | Committee Report |
| 913NPRR-06 PRS Voting Ballot 041119 | xls | Apr 22 '19 | Revision Request Ballot |
Meetings That Took It Up 9
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Apr 11 '19 | PRS Meeting | PRS | Concluded |
| Apr 4 '19 | ROS Meeting | ROS | Concluded |
| Mar 14 '19 | PRS Meeting | PRS | Concluded |
| Mar 12 '19 | PLWG Meeting | PLWG | Concluded |
| Mar 7 '19 | ROS Meeting | ROS | Concluded |
| Feb 20 '19 | PLWG Meeting | PLWG | Concluded |
| Feb 14 '19 | PRS Meeting | PRS | Concluded |
| Feb 7 '19 | ROS Meeting | ROS | Concluded |
| Jan 17 '19 | PRS Meeting | PRS | Concluded |