NPRR #912 · Revision Request
NPRR912 Settlement of Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2018-12-13
Approved2019-04-09
Sections Affected
2.25.5.25.7.4.1.15.7.7 (new)6.6.12 (new)6.6.12.1 (new)6.6.12.2 (new)6.6.12.3 (new)6.7.5and 9.14.9 (new)
Summary
This Nodal Protocol Revision Request (NPRR) addresses the Settlement of Switchable Generation Resources (SWGRs) that receive a Reliability Unit Commitment (RUC) instruction to switch from a non-ERCOT Control Area to the ERCOT Control Area. The NPRR provides a Make-Whole Payment for a SWGR when the SWGR’s Real-Time revenues in ERCOT are not sufficient to cover certain specified costs the SWGR may have incurred in complying with such a RUC instruction. As proposed in this NPRR, eligible costs include costs of starting up and operating, energy and Ancillary Service imbalance charges assessed by the non-ERCOT Control Area Operator, and additional fuel costs directly attributable to the switch. SWGRs may recover incremental startup and operating costs above those described below based on proxy costs created by ERCOT if the SWGR does not have approved verifiable costs. The SWGR Make-Whole Payment will include costs to shutdown in the non-ERCOT grid, start in ERCOT, shutdown in ERCOT, and re-start in the non-ERCOT grid, when the SWGR switches back to the non-ERCOT control area within 24 hours of being released from the RUC. To qualify for the Make-Whole Payment, the SWGR must be operating in the non-ERCOT Control Area at the time ERCOT issues the RUC instruction. Qualified Scheduling Entities (QSEs) representing SWGRs must file a Settlement and billing dispute to trigger the Make-Whole Payment calculation. Finally, ERCOT has included language that would codify ERCOT’s intention to issue a switch directive to an SWGR only in the limited circumstances in which both the SWGR is needed to address an actual or anticipated Emergency Condition and the non-ERCOT Control Area Operator has released the SWGR to ERCOT.
Action Log 5 milestones
-
Dec 13
PRSDeferred/Tabled→ Language Consideration
-
Feb 14
PRSRecommended for Approval→ Impact Analysis Consideration
-
Mar 14
PRSRecommended for Approval→ Revision Request Consideration
-
Mar 27
TACRecommended for Approval→ Revision Request Consideration
-
Apr 9
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Feb 14 '19 | PRS | to recommend approval of NPRR912 as amended by the 2/7/19 WMS comments | Passed |
| Mar 14 '19 | PRS | to endorse and forward to TAC the 2/14/19 PRS Report as revised by PRS and the Impact Analysis for NPRR912 | Passed |
Documents 18
| Name | Type | Posted | Classification |
|---|---|---|---|
| 912NPRR-01 Settlement of SWGRs Instructed to Switch to ERCOT 112818 | doc | Nov 28 '18 | Revision Request |
| 912NPRR-02 Impact Analysis 112818 | doc | Nov 28 '18 | Staff Report |
| 912NPRR-03 Tenaska Energy Comments 121318 | doc | Dec 13 '18 | Revision Request Comments |
| 912NPRR-04 PRS Report 121318 | doc | Dec 14 '18 | Committee Report |
| 912NPRR-05 Tenaska Energy Comments 010419 | doc | Jan 4 '19 | Revision Request Comments |
| 912NPRR-06 GSEC Comments 010719 | doc | Jan 7 '19 | Revision Request Comments |
| 912NPRR-07 TCPA Comments 010819 | doc | Jan 8 '19 | Revision Request Comments |
| 912NPRR-08 ERCOT Comments 010819 | doc | Jan 8 '19 | Revision Request Comments |
| 912NPRR-09 WMS Comments 011019 | doc | Jan 10 '19 | Revision Request Comments |
| 912NPRR-10 Joint Comments 020419 | doc | Feb 4 '19 | Revision Request Comments |
| 912NPRR-11 Tenaska Comments 020519 | doc | Feb 5 '19 | Revision Request Comments |
| 912NPRR-12 ERCOT Comments 020619 | doc | Feb 6 '19 | Revision Request Comments |
| 912NPRR-13 WMS Comments 020719 | doc | Feb 7 '19 | Revision Request Comments |
| 912NPRR-14 WMS Voting Ballot 020719 | xls | Feb 7 '19 | Revision Request Ballot |
| 912NPRR-15 PRS Report 021419 | doc | Feb 18 '19 | Committee Report |
| 912NPRR-16 PRS Report 031419 | doc | Mar 19 '19 | Committee Report |
| 912NPRR-17 TAC Report 032719 | doc | Mar 28 '19 | Committee Report |
| 912NPRR-18 Board Report 040919 | doc | Apr 12 '19 | Committee Report |
Meetings That Took It Up 10
| Date | Meeting | Committee | Status |
|---|---|---|---|
| May 6 '19 | CMWG Meeting | CMWG | Concluded |
| Apr 9 '19 | Board of Directors Meeting | BOARD | Concluded |
| Mar 27 '19 | TAC Meeting | TAC | Concluded |
| Mar 14 '19 | PRS Meeting | PRS | Concluded |
| Feb 14 '19 | PRS Meeting | PRS | Concluded |
| Feb 6 '19 | WMS Meeting | WMS | Concluded |
| Jan 25 '19 | WMWG Meeting | WMWG | Concluded |
| Jan 17 '19 | PRS Meeting | PRS | Concluded |
| Jan 9 '19 | WMS Meeting | WMS | Concluded |
| Dec 13 '18 | PRS Meeting | PRS | Concluded |