NPRR888 4-Coincident Peak Adjustment Methodology
- PRS Sep 13 '18
- TAC Sep 26 '18
- BOARD Oct 9 '18
- PUCT —
ReasonAdministrative
Created2018-08-16
Approved2018-10-09
Sections Affected
9.17.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the 4-Coincident Peak (4-CP) adjustment methodology that was implemented in conjunction with NPRR830, Revision of 4-Coincident Peak Methodology. This methodology was endorsed by the Wholesale Market Subcommittee (WMS) at its May 2, 2018 meeting.
Timeline
- Jul 24
-
Aug 16
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR888 as submitted” — Passed→ Impact Analysis Consideration
-
Sep 13
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 8/16/18 PRS Report and Impact Analysis for NPRR888” — Passed→ Revision Request Consideration
-
Sep 26
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR888 as recommended by PRS in the 9/13/18 PRS Report” — Passed→ Revision Request Consideration
-
Oct 9