NPRR846 Allow Previously Committed ERS Resources to Participate in MRA Agreements and Other ERS Items
ReasonAddresses current operational issues; Administrative; Regulatory Requirements
Created2017-09-14
Approved2017-12-12
Sections Affected
2.13.14.3.18.1.3.1.18.1.3.1.28.1.3.1.3.18.1.3.1.3.28.1.3.1.3.38.1.3.1.48.1.3.28.1.3.3.18.1.3.3.2
Summary
This Nodal Protocol Revision Request (NPRR) addresses a number of changes pertaining to the Emergency Response Service (ERS): 1) Allows previously committed ERS Resources to participate in Must-Run Alternative (MRA) Agreements as ordered in Public Utility Commission of Texas (PUCT) Project No. 45927, Rulemaking Regarding Emergency Response Service. 2) Modifies the methodology for evaluating the performance during the first partial interval for ERS Loads on the alternate baseline. The current methodology produces incorrect results when the average Load for the first partial interval is above its maximum base Load, but in reality the Load responded according to the instruction. 3) Provides edits pertaining to the self-serve capacity associated with an ERS Generator. This change is necessary to define the acceptable parameters for self-serve capacity. 4) Adds Protocol language that will set the ERSTESTPF to significantly lower values and in some instances to zero for ERS Resources with three consecutive test failures in a 365 day period. In those instances where the ERSTESTPF are set to zero there will be no ERS payment for these Resources for the Standard Contract Term for which the third test failure occurred. 5) Provides additional administrative changes and clarifications to existing Protocol language pertaining to ERS.
Action Log 5 milestones
-
Sep 14
PRSDeferred/Tabled→ Language Consideration
-
Oct 12
PRSRecommended for Approval→ Impact Analysis Consideration
-
Nov 9
PRSRecommended for Approval→ Revision Request Consideration
-
Nov 30
TACRecommended for Approval→ Revision Request Consideration
-
Dec 12
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 12 '17 | PRS | To recommend approval of NPRR846 as revised by PRS. | Passed |
| Nov 9 '17 | PRS | To endorse and forward to TAC the 10/12/17 PRS Report as amended by the 11/2/17 ERCOT comments and the Impact Analysis for NPRR846. | Passed |
Documents 10
| Name | Type | Posted | Classification |
|---|---|---|---|
| 846NPRR-01 Allow Previously Committed ERS Resources to Participate in MRA Agreements and Other ERS Items 082517 | doc | Aug 25 '17 | Revision Request |
| 846NPRR-02 Impact Analysis 082517 | doc | Aug 25 '17 | Staff Report |
| 846NPRR-03-PRS Report 091417 | doc | Oct 11 '17 | Committee Report |
| 846NPRR-04 WMS Comments 092717 | doc | Sep 27 '17 | Revision Request Comments |
| 846NPRR-05 PRS Report 101217 | doc | Oct 16 '17 | Committee Report |
| 846NPRR-06 ERCOT Comments 103017 | doc | Oct 30 '17 | Revision Request Comments |
| 846NPRR-07 ERCOT Comments 110217 | doc | Nov 2 '17 | Revision Request Comments |
| 846NPRR-08 PRS Report 110917 | doc | Nov 14 '17 | Committee Report |
| 846NPRR-09 TAC Report 113017 | doc | Dec 1 '17 | Committee Report |
| 846NPRR-10 Board Report 121217 | doc | Dec 13 '17 | Committee Report |
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 12 '17 | Board of Directors Meeting | BOARD | Concluded |
| Nov 30 '17 | TAC Meeting | TAC | Concluded |
| Nov 9 '17 | PRS Meeting | PRS | Concluded |
| Oct 12 '17 | PRS Meeting | PRS | Concluded |
| Sep 27 '17 | WMS Meeting | WMS | Concluded |
| Sep 14 '17 | PRS Meeting | PRS | Concluded |