NPRR #845 · Revision Request
NPRR845 RMR Process and Agreement Revisions
- PRS Jul 19 '18
- TAC Sep 26 '18
- BOARD Oct 9 '18
- PUCT —
ReasonAddresses current operational issues. Market efficiencies / enhancements
Created2017-08-11
Approved2018-10-09
Sections Affected
1.3.1.23.14.1.23.14.1.93.14.1.113.14.1.123.14.1.12 (new)3.14.1.13 (new)3.14.1.143.14.1.15 (ref)3.14.1.163.14.1.16 (new)3.14.1.173.14.1.186.6.6.16.6.6.622Band 22E
Summary
This Nodal Protocol Revision Request (NPRR) incorporates a number of revisions to improve the effectiveness of the Reliability Must-Run (RMR) process.
Timeline
- Jul 27
-
Aug 11
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR845 and refer the issue to WMS” — Passed→ PRS for consideration
- Sep 6
- Sep 14
-
Sep 15
Listed without action at 11 meetings (Sep 15 '17 – Jan 10 '18)
- Jan 18
-
Jan 31
Listed without action at 14 meetings (Jan 31 '18 – Jun 6 '18)
-
Jun 14
PRS PRS MeetingPRSRecommended for Approval Amended by the Jun 7 '18 WMS comments“To recommend approval of NPRR845 as amended by the 6/7/18 WMS comments” — Passed→ PRS for Impact Analysis review
-
Jul 19
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC priority 2018 · rank 2280“To endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR845 with a recommended priority of 2018 and rank of 2280” — Passed→ TAC for consideration
- Jul 26
-
Sep 26
TAC TAC MeetingTACRecommended for Approval Amended by the Sep 13 '18 ERCOT comments“To recommend approval of NPRR845 as recommended by PRS in the 7/19/18 PRS Report as amended by the 9/13/18 ERCOT comments” — Passed→ Board for consideration
-
Oct 9
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR845 as recommended by TAC in the 9/26/18 TAC Report” — Passed
-
Mar 26
Listed without action at 1 meeting