NPRR #843 · Revision Request
NPRR843 Short-Term System Adequacy and AS Offer Disclosure Reports Additions
- PRS Nov 9 '17
- TAC Nov 30 '17
- BOARD Dec 12 '17
- PUCT —
ReasonMeets Strategic goals; Regulatory requirements
Created2017-08-11
Approved2017-12-12
Sections Affected
3.2.3 and 3.2.5
Summary
This Nodal Protocol Revision Request (NPRR) addresses four separate reporting items in Section 3, Management Activities for the ERCOT System, of the Nodal Protocols. 1. This NPRR makes changes to the logic for the Short-Term System Adequacy Reports for more consistent treatment of Resource Statuses in reporting available capacity. Also, more specific language is added to provide clarity to end users of the reports. 2. This NPRR creates a new report which will show the portion of Ancillary Service Offers at or above 50 times the Fuel Index Price (FIP) when the Market Clearing Price for Capacity (MCPC) of that Ancillary Service exceeds 50 times FIP. This posting will occur seven days after the Operating Day, as required by P.U.C. SUBST. R. 25.505, Resource Adequacy in the Electric Reliability Council of Texas Power Region. 3. Additional elements are added to the “48-Hour Highest Price AS Offer Selected” report to also include the highest-priced Ancillary Service Offer selected in a Supplemental Ancillary Services Market (SASM). 4. A 60-day SASM disclosure report is created to provide transparency into Ancillary Service Offers and awards for any SASMs that may have been executed for a period within an Operating Day.
Timeline
- Jul 26
-
Aug 11
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR843 and refer the issue to WMS.” — Passed→ Language Consideration
- Sep 6
- Sep 14
-
Sep 15
Listed without action at 2 meetings (Sep 15 '17 – Sep 27 '17)
-
Oct 12
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR843 as submitted.” — Passed→ Impact Analysis Consideration
-
Nov 9
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC priority 2018 · rank 170“To endorse and forward to TAC the 10/12/17 PRS Report and Impact Analysis for NPRR843 with a recommended priority of 2018 and rank of 170.” — Passed→ Revision Request Consideration
-
Nov 30
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR843 as recommended by PRS in the 11/9/17 PRS Report.” — Passed→ Revision Request Consideration
-
Dec 12
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR843 as recommended by TAC in the 11/30/17 TAC Report.” — Passed
-
—