NPRR #840 · Revision Request

NPRR840  Implementation of Infeasible Ancillary Service Protocol Revisions

Approved sponsor ERCOT posted 2017-07-25 ercot.com
ReasonAddresses current operational issues
Created2017-08-11
Approved2017-10-17
Sections Affected
6.4.9.1.26.4.9.2and 6.7.2.1
Summary
This Nodal Protocol Revision Request (NPRR) synchronizes the implementation of NPRR782, Settlement of Infeasible Ancillary Services Due to Transmission Constraints, by removing the two hour advance notice period inadvertently left in Protocol language when NPRR782 was approved.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
840NPRR-01 Implementation of Infeasible Ancillary Service Protocol Revisions 072517 doc Jul 25 '17 Revision Request
840NPRR-02 Impact Analysis 072517 doc Jul 25 '17 Staff Report
840NPRR-03 PRS Report 081117 doc Aug 14 '17 Committee Report
840NPRR-04 PRS Report 091417 doc Sep 15 '17 Committee Report
840NPRR-05 TAC Report 092817 doc Oct 2 '17 Committee Report
840NPRR-06 Board Report 101717 doc Oct 19 '17 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Oct 17 '17 Board of Directors Meeting BOARD Concluded
Sep 28 '17 TAC Meeting TAC Concluded
Sep 14 '17 PRS Meeting PRS Concluded
Aug 11 '17 PRS Meeting PRS Concluded