NPRR #836 · Revision Request
NPRR836 Incorporation of Other Binding Document Forms into Protocol Section 23
ReasonMarket efficiencies or enhancements
Created2017-07-20
Approved2017-10-17
Sections Affected
3.1.4.13.6.23.19.116.316.3.1.116.3.216.416.8.116.8.221.123 A (new)23 B (new)23 C (new)23 D (new)23 E (new)23 F (new)23 G (new)23 H (new)23 I (new)23 J (new)and 23 K (new)
Summary
This Nodal Protocol Revision Request (NPRR) incorporates the following Other Binding Documents into the Protocols as a new Section 23, Forms. Currently, changes to these forms are made unilaterally by ERCOT: Congestion Revenue Right (CRR) Account Holder Application Form, Load Serving Entities (LSE) Application Form, Managed Capacity Declaration Form, Market Participant Agency Agreement Form, Notice of Change of Information, QSE Agency Agreement Form, QSE Application Form, Qualified Scheduling Entity Acknowledgement, Resource Entity Registration Form, Transmission/Distribution Service Provider Registration Form, and WAN Agreement. This NPRR also allows changes to these Section 23 forms to be made using the Administrative NPRR process.
Action Log 4 milestones
-
Jul 20
PRSRecommended for Approval→ PRS for Impact Analysis review
-
Aug 11
PRSRecommended for Approval→ TAC for consideration
-
Aug 24
TACRecommended for Approval→ Board for consideration
-
Oct 17
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 836NPRR-01 Incorporation of Other Binding Document Forms into Protocol Section 23 062117 | doc | Jun 21 '17 | Revision Request |
| 836NPRR-02 Impact Analysis 062117 | doc | Jun 21 '17 | Staff Report |
| 836NPRR-03 PRS Report 072017 | doc | Jul 20 '17 | Committee Report |
| 836NPRR-04 PRS Report 081117 | doc | Aug 16 '17 | Committee Report |
| 836NPRR-05 TAC Report 082417 | doc | Aug 24 '17 | Committee Report |
| 836NPRR-06 Board Report 101717 | doc | Oct 17 '17 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Oct 17 '17 | Board of Directors Meeting | BOARD | Concluded |
| Aug 24 '17 | TAC Meeting | TAC | Concluded |
| Aug 11 '17 | PRS Meeting | PRS | Concluded |
| Jul 20 '17 | PRS Meeting | PRS | Concluded |