ERCOT·WATCH Search ercot.com  ⌕
NPRR #801 · Revision Request

NPRR801  Non-Controllable Load Resource MW in PRC

Approved sponsor ERCOT posted 2016-08-31 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2016-09-15
Approved2016-12-13
Sections Affected
6.5.7.56.7.5
Summary
This Nodal Protocol Revision Request (NPRR) revises the Physical Responsive Capability (PRC) calculation from including the Responsive Reserve (RRS) service MW responsibility from Load Resources controlled by high-set under frequency relays to including all MW from these Load Resources from their current output to their Low Power Consumption (LPC) capped at 150% of the Qualified Scheduling Entity’s (QSE’s) RRS responsibility from non-Controllable Load Resources. The Operating Reserve Demand Curve (ORDC) reserves are adjusted in the Other Binding Document (OBD) to align with the PRC change. The Ancillary Service imbalance Settlement is changed to align with the change to the ORDC reserves.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Oct 13 '16PRS To endorse and forward to TAC the 9/15/16 PRS Report as revised by PRS and the Impact Analysis for NPRR801 with a recommended priority of 2017 and a rank of 1870.Passed
Documents 6
NameTypePostedClassification
801NPRR-01 Non Controllable Load Resource MW in PRC 083116 doc Aug 31 '16 Revision Request
801NPRR-02 Impact Analysis 083116 doc Aug 31 '16 Staff Report
801NPRR-03 PRS Report 091516 doc Oct 6 '16 Committee Report
801NPRR-04 PRS Report 101316 doc Oct 17 '16 Committee Report
801NPRR-05 TAC Report 102716 doc Oct 31 '16 Committee Report
801NPRR-06 Board Report 121316 doc Dec 13 '16 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Dec 13 '16 Board of Directors Meeting BOARD Concluded
Oct 27 '16 TAC Meeting TAC Concluded
Oct 13 '16 PRS Meeting PRS Concluded
Sep 21 '16 CWG/MCWG Meeting CREDITWG Concluded
Sep 15 '16 PRS Meeting PRS Concluded