NPRR #799 · Revision Request
NPRR799 Updates to Outages of Transmission Facilities
- PRS Mar 9 '17
- TAC Mar 23 '17
- BOARD Apr 4 '17
- PUCT —
ReasonMarket efficiencies or enhancements
Created2016-09-15
Approved2017-04-04
Sections Affected
3.1.23.1.5.13
Summary
This Nodal Protocol Revision Request (NPRR) introduces requirements for submitting updates to the Outage Scheduler for completed or started Outages on Transmission Facilities.
Timeline
- Aug 25
-
Sep 15
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS Referred → WMS“To table NPRR799 and refer the issue to ROS and WMS.” — Passed→ Language Consideration
- Oct 6
-
Oct 13
Listed without action at 2 meetings (Oct 13 '16 – Oct 17 '16)
- Oct 20
-
Nov 2
Listed without action at 2 meetings (Nov 2 '16 – Nov 3 '16)
- Nov 10
-
Nov 14
Listed without action at 2 meetings (Nov 14 '16 – Nov 17 '16)
- Dec 1
-
Dec 16
Listed without action at 3 meetings (Dec 16 '16 – Jan 12 '17)
- Jan 13
-
Jan 19
PRS PRS MeetingPRSDeferred/Tabled“To table NPRR799 for one month.” — Passed→ Language Consideration
- Jan 30
-
Feb 1
Listed without action at 1 meeting
-
Feb 9
PRS PRS MeetingPRSRecommended for Approval Amended by the Jan 19 '17 Morgan Stanley comments“To recommend approval of NPRR799 as amended by the 1/19/17 Morgan Stanley comments.” — Passed→ Impact Analysis Consideration
-
Mar 9
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To forward to TAC the 2/9/17 PRS Report and the Impact Analysis for NPRR799” — Passed→ Revision Request Consideration
-
Mar 23
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR799 as recommended by PRS in the 3/9/17 PRS Report.” — Passed→ Revision Request Consideration
-
Apr 4
BOARD Board of Directors MeetingBOARDApproved“Approved NPRR799 as recommended by TAC in the 3/23/17 TAC Report.” — Passed
-
—
Posted since the last meeting