NPRR790  Addition of Phase Angle Limits to the Network Operations Model

Approved sponsor ERCOT posted 2016-07-20 ercot.com
ReasonRegulatory requirements
Created2016-08-11
Approved2016-12-13
Sections Affected
3.10.7.1.3
Summary
This Nodal Protocol Revision Request (NPRR) adds phase angle limitations to the ERCOT Network Operations Modeling process.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Sep 15 '16PRS To recommend approval of NPRR790 as amended by the 9/6/16 CNP comments.Passed
Documents 12
NameTypePostedClassification
790NPRR-01 Addition of Phase Angle Limits to the Network Operations Model 072016 docx Aug 9 '16 Revision Request
790NPRR-02 Impact Analysis 072016 doc Jul 20 '16 Staff Report
790NPRR-03 Luminant Comments 072716 docx Aug 9 '16 Revision Request Comments
790NPRR-04 Oncor Comments 080516 doc Aug 5 '16 Revision Request Comments
790NPRR-05 ERCOT Comments 080916 doc Aug 9 '16 Revision Request Comments
790NPRR-06 PRS Report 081116 doc Aug 16 '16 Committee Report
790NPRR-07 CNP Comments 090616 doc Sep 6 '16 Revision Request Comments
790NPRR-08 ROS Comments 090816 doc Sep 9 '16 Revision Request Comments
790NPRR-09 PRS Report 091516 doc Sep 19 '16 Committee Report
790NPRR-10 PRS Report 101316 doc Oct 18 '16 Committee Report
790NPRR-11 TAC Report 102716 doc Oct 28 '16 Committee Report
790NPRR-12 Board Report 121316 doc Dec 15 '16 Committee Report
Meetings That Took It Up 10
DateMeetingCommitteeStatus
Jan 17 '17 NDSWG Meeting NDSWG Concluded
Dec 13 '16 Board of Directors Meeting BOARD Concluded
Nov 8 '16 NRWG Meeting NRWG Concluded
Oct 27 '16 TAC Meeting TAC Concluded
Oct 13 '16 PRS Meeting PRS Concluded
Sep 21 '16 CWG/MCWG Meeting CREDITWG Concluded
Sep 15 '16 PRS Meeting PRS Concluded
Sep 8 '16 ROS Meeting ROS Concluded
Aug 18 '16 OWG Meeting OWG Concluded
Aug 11 '16 PRS Meeting PRS Concluded