NPRR #783 · Revision Request
NPRR783 Revision of Network Operations Model Consistency Audit Requirement
- PRS Oct 13 '16
- TAC Oct 27 '16
- BOARD Dec 13 '16
- PUCT —
ReasonAddresses current operational issues / regulatory requirement
Created2016-06-16
Approved2016-12-13
Sections Affected
3.10
Summary
This Nodal Protocol Revision Request (NPRR) revises an outdated requirement for an independent audit to confirm consistency between ERCOT operations models, yet retains the underlying requirement of model consistency.
Timeline
- Jun 1
-
Jun 16
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS“To table NPRR783 and refer the issue to ROS” — Passed→ PRS for consideration
- Jul 7
- Jul 14
-
Aug 4
Listed without action at 3 meetings (Aug 4 '16 – Sep 8 '16)
-
Sep 15
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR783 as submitted” — Passed→ PRS for Impact Analysis review
- Sep 21
-
Oct 13
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 9/15/16 PRS Report and Impact Analysis for NPRR783” — Passed→ TAC for consideration
-
Oct 27
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR783 as recommended by PRS in the 10/13/16 PRS Report” — Passed→ Board for consideration
-
Dec 13
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR783 as recommended by TAC in the 10/27/16 TAC Report” — Passed