NPRR #776 · Revision Request
NPRR776 Voltage Set Point Communication
ReasonAddresses current operational issues
Created2016-06-16
Approved2017-04-04
Sections Affected
3.10.7.5.26.5.7.7
Summary
This Nodal Protocol Revision Request (NPRR) aligns language with currently used verbal communication practices between Transmission Service Providers (TSP), Qualified Scheduling Entities (QSE), and Generation Resources. This NPRR also identifies a new telemetered data point (Voltage Set Point) and identification of the Point of Interconnection (POI) kV measurements to be used relative to the Voltage Set Point which is to be provided by the TSP to ERCOT, the QSE, and the Generation Resource.
Action Log 5 milestones
-
Jun 16
PRSDeferred/Tabled→ PRS for consideration
-
Feb 9
PRSRecommended for Approval→ PRS for Impact Analysis review
-
Mar 9
PRSRecommended for Approval→ TAC for consideration
-
Mar 23
TACRecommended for Approval→ Board for consideration
-
Apr 4
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Feb 9 '17 | PRS | To recommend approval of NPRR776 as amended by the 1/23/17 ERCOT comments | Passed |
| Mar 9 '17 | PRS | To endorse and forward to TAC the 2/9/17 PRS Report and Revised Impact Analysis for NPRR776 with a recommended priority of 2017 and rank of 1970 | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Apr 27 '17 | TAC | Motion Passes | 26 | 0 | 0 | xls |
Documents 14
| Name | Type | Posted | Classification |
|---|---|---|---|
| 776NPRR-01 Voltage Set Point Communication 051816 | doc | May 18 '16 | Revision Request |
| 776NPRR-02 Impact Analysis 051816 | doc | May 18 '16 | Staff Report |
| 776NPRR-03 NRG Comments 060116 | doc | Jun 1 '16 | Revision Request Comments |
| 776NPRR-04 PRS Report 061616 | doc | Jun 20 '16 | Committee Report |
| 776NPRR-05 WMS Comments 070716 | doc | Jul 7 '16 | Revision Request Comments |
| 776NPRR-06 ROS Comments 080416 | doc | Aug 5 '16 | Revision Request Comments |
| 776NPRR-07 ERCOT Comments 012317 | doc | Jan 23 '17 | Revision Request Comments |
| 776NPRR-08 WMS Comments 020217 | doc | Feb 2 '17 | Revision Request Comments |
| 776NPRR-09 ROS Comments 020317 | doc | Feb 3 '17 | Revision Request Comments |
| 776NPRR-10 PRS Report 020917 | doc | Feb 13 '17 | Committee Report |
| 776NPRR-11 Revised Impact Analysis 030717 | doc | Mar 7 '17 | Staff Report |
| 776NPRR-12 PRS Report 030917 | doc | Mar 10 '17 | Committee Report |
| 776NPRR-13 TAC Report 032317 | doc | Mar 24 '17 | Committee Report |
| 776NPRR-14 Board Report 040417 | doc | Apr 4 '17 | Committee Report |
Meetings That Took It Up 49
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Mar 21 '19 | Resource Integration Workshop | RIWG | Concluded |
| Jan 23 '18 | NDSWG Meeting | NDSWG | Concluded |
| Oct 17 '17 | NDSWG Meeting | NDSWG | Concluded |
| Jul 18 '17 | NDSWG Meeting | NDSWG | Concluded |
| Apr 24 '17 | TAC Information Session - WebEx Only | TAC | Concluded |
| Apr 18 '17 | NDSWG Meeting | NDSWG | Concluded |
| Apr 4 '17 | Board of Directors Meeting | BOARD | Concluded |
| Mar 23 '17 | TAC Meeting | TAC | Concluded |
| Mar 9 '17 | PRS Meeting | PRS | Concluded |
| Mar 2 '17 | ROS Meeting | ROS | Concluded |
| Feb 15 '17 | OWG Meeting | OWG | Concluded |
| Feb 9 '17 | PRS Meeting | PRS | Concluded |
| Feb 2 '17 | ROS Meeting | ROS | Concluded |
| Feb 1 '17 | WMS Meeting | WMS | Concluded |
| Jan 30 '17 | QMWG Meeting | QMWG | Concluded |
| Jan 19 '17 | PRS Meeting | PRS | Concluded |
| Jan 17 '17 | OWG Meeting | OWG | Concluded |
| Jan 13 '17 | QMWG Meeting | QMWG | Concluded |
| Jan 12 '17 | ROS Meeting | ROS | Concluded |
| Jan 11 '17 | WMS Meeting | WMS | Concluded |
| Dec 16 '16 | OWG Meeting | OWG | Concluded |
| Dec 1 '16 | PRS Meeting | PRS | Concluded |
| Nov 17 '16 | OWG Meeting | OWG | Concluded |
| Nov 10 '16 | PRS Meeting | PRS | Concluded |
| Nov 3 '16 | ROS Meeting | ROS | Concluded |
| Nov 2 '16 | WMS Meeting | WMS | Concluded |
| Oct 20 '16 | OWG Meeting | OWG | Concluded |
| Oct 17 '16 | WMS Meeting | WMS | Concluded |
| Oct 14 '16 | QMWG Meeting | QMWG | Concluded |
| Oct 13 '16 | PRS Meeting | PRS | Concluded |
| Oct 6 '16 | ROS Meeting | ROS | Concluded |
| Sep 22 '16 | OWG Meeting | OWG | Concluded |
| Sep 19 '16 | QMWG Meeting | QMWG | Concluded |
| Sep 15 '16 | PRS Meeting | PRS | Concluded |
| Sep 8 '16 | ROS Meeting | ROS | Concluded |
| Sep 7 '16 | WMS Meeting | WMS | Concluded |
| Aug 30 '16 | QMWG Meeting | QMWG | Concluded |
| Aug 18 '16 | OWG Meeting | OWG | Concluded |
| Aug 11 '16 | PRS Meeting | PRS | Concluded |
| Aug 4 '16 | ROS Meeting | ROS | Concluded |
| Aug 3 '16 | WMS Meeting | WMS | Concluded |
| Jul 21 '16 | OWG Meeting | OWG | Concluded |
| Jul 18 '16 | QMWG Meeting | QMWG | Concluded |
| Jul 14 '16 | PRS Meeting | PRS | Concluded |
| Jul 7 '16 | ROS Meeting | ROS | Concluded |
| Jul 6 '16 | WMS Meeting | WMS | Concluded |
| Jun 23 '16 | OWG Meeting | OWG | Concluded |
| Jun 16 '16 | PRS Meeting | PRS | Concluded |
| May 19 '16 | OWG Meeting | OWG | Concluded |