NPRR #767 · Revision Request
NPRR767 Commitment by RUC for Long Lead Time Resource
ReasonMarket efficiencies or enhancements
Created2016-05-12
Approved2016-10-11
Sections Affected
5.6.2
Summary
This Nodal Protocol Revision Request (NPRR) changes the eligibility check for the startup portion of the Reliability Unit Commitment (RUC) Make-Whole Payment. Resources with lead times longer than six hours may submit a Settlement dispute to have their Resource-specific startup times considered when determining eligibility for Startup Costs to be included in the RUC Make-Whole Payment calculation.
Action Log 4 milestones
-
May 12
PRSRecommended for Approval→ Impact Analysis Consideration
-
Jun 16
PRSRecommended for Approval→ Revision Request Consideration
-
Jul 28
TACRecommended for Approval→ Revision Request Consideration
-
Oct 11
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 767NPRR-01 Commitment by RUC for Long Lead Time Resource 042116 | doc | Apr 21 '16 | Revision Request |
| 767NPRR-02 Impact Analysis 042116 | doc | Apr 21 '16 | Staff Report |
| 767NPRR-03 PRS Report 051216 | doc | May 13 '16 | Committee Report |
| 767NPRR-04 PRS Report 061616 | doc | Jun 20 '16 | Committee Report |
| 767NPRR-05 TAC Report 072816 | doc | Aug 1 '16 | Committee Report |
| 767NPRR-06 Board Report 101116 | doc | Oct 13 '16 | Committee Report |
Meetings That Took It Up 7
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Aug 9 '16 | Board of Directors Meeting | BOARD | Concluded |
| Jul 28 '16 | TAC Meeting | TAC | Concluded |
| Jun 16 '16 | PRS Meeting | PRS | Concluded |
| May 18 '16 | CWG/MCWG Meeting | CREDITWG | Concluded |
| May 13 '16 | QMWG Meeting | QMWG | Concluded |
| May 12 '16 | PRS Meeting | PRS | Concluded |
| May 4 '16 | WMS Meeting | WMS | Concluded |