NPRR761  As-Built Clarification to NPRR515, Day-Ahead Market Self-Commitment of Generation Resources

Approved sponsor ERCOT posted 2016-03-09 ercot.com
ReasonAdministrative, Other
Created2016-04-14
Approved2016-06-14
Sections Affected
4.6.2.3
Summary
Nodal Protocol Revision Request (NPRR) 515, Day-Ahead Market Self-Commitment of Generation Resources, adds a Day-Ahead Market (DAM) mechanism for self-committing Generation Resources on an hourly basis. If a self-committed hour is contiguous with a DAM committed hour the DAM considers the Resource as having no cost to start up. This NPRR clarifies that a Resource will not be eligible for Day-Ahead Make-Whole Payment Startup Cost compensation when the DAM considers the Resource as having no cost to startup, per NPRR515.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
761NPRR-01 As Built Clarification to NPRR515 Day Ahead Market Self Commitment of Generation Resources 030916 doc Mar 9 '16 Revision Request
761NPRR-02 Impact Analysis 030916 doc Mar 9 '16 Staff Report
761NPRR-03 PRS Report 041416 doc Apr 18 '16 Committee Report
761NPRR-04 PRS Report 051216 doc May 16 '16 Committee Report
761NPRR-05 TAC Report 052616 doc May 27 '16 Committee Report
761NPRR-06 Board Report 061416 doc Jun 15 '16 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Jun 14 '16 Board of Directors Meeting BOARD Concluded
May 26 '16 TAC Meeting TAC Concluded
May 12 '16 PRS Meeting PRS Concluded
Apr 20 '16 CWG/MCWG Meeting CREDITWG Concluded
Apr 14 '16 PRS Meeting PRS Concluded