NPRR #758 · Revision Request
NPRR758 Improved Transparency for Outages Potentially Having a High Economic Impact
ReasonAddresses current operation issues; market efficiencies/enhancements
Created2016-04-14
Approved2016-06-14
Sections Affected
2.12.23.1.13.1.23.1.3.13.1.4.13.1.4.33.1.4.43.1.4.53.1.5.13.1.5.23.1.5.63.1.5.73.1.5.83.1.5.113.1.5.133.1.8 (new)6.5.9.5
Summary
This Nodal Protocol Revision Request (NPRR) introduces language to: identify Outages that have historically resulted in high congestion costs, as adjusted through a stakeholder review process to account for upgrades and other changes that would affect the fidelity of this list as an indicator of Outages that might cause future congestion; encourage earlier submission of these Outages; formalize the process of rescheduling these Outages when they must be moved due to Forced Outages or later-arriving generator Outages; and provide improved transparency to Market Participants when Outages with this potential congestion impact are submitted with less than 90 days’ notice. Specific items proposed within this NPRR include: identification and posting of High Impact Transmission Elements (HITEs) and High Impact Outages (HIOs); and introduction of a Rescheduled Outage type.
Action Log 4 milestones
-
Apr 14
PRSRecommended for Approval→ PRS for Impact Analysis review
-
May 12
PRSRecommended for Approval→ TAC for consideration
-
May 26
TACRecommended for Approval→ Board for consideration
-
Jun 14
BOARDApproved
Documents 10
| Name | Type | Posted | Classification |
|---|---|---|---|
| 758NPRR-01 Improved Transparency for Outages Potentially Having a High Economic Impact 022616 | doc | Feb 26 '16 | Revision Request |
| 758NPRR-02 Impact Analysis 022616 | doc | Feb 26 '16 | Staff Report |
| 758NPRR-03 CenterPoint Comments 040716 | doc | Apr 7 '16 | Revision Request Comments |
| 758NPRR-04 Inertia Power Comments 041216 | doc | Apr 12 '16 | Revision Request Comments |
| 758NPRR-05 Luminant Comments 041316 | doc | Apr 13 '16 | Revision Request Comments |
| 758NPRR-06 PRS Report 041416 | doc | Apr 19 '16 | Committee Report |
| 758NPRR-07 ERCOT Comments 050516 | doc | May 5 '16 | Revision Request Comments |
| 758NPRR-08 PRS Report 051216 | doc | May 16 '16 | Committee Report |
| 758NPRR-09 TAC Report 052616 | doc | May 31 '16 | Committee Report |
| 758NPRR-10 Board Report 061416 | doc | Jun 15 '16 | Committee Report |
Meetings That Took It Up 12
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Aug 1 '17 | OCWG Meeting | OCWG | Concluded |
| May 15 '17 | OCWG Meeting | OCWG | Concluded |
| Jan 23 '17 | OCITF Meeting | OCITF | Concluded |
| Jun 14 '16 | Board of Directors Meeting | BOARD | Concluded |
| Jun 10 '16 | QMWG Meeting | QMWG | Concluded |
| May 26 '16 | TAC Meeting | TAC | Concluded |
| May 12 '16 | PRS Meeting | PRS | Concluded |
| May 5 '16 | ROS Meeting | ROS | Concluded |
| May 4 '16 | WMS Meeting | WMS | Concluded |
| Apr 20 '16 | CWG/MCWG Meeting | CREDITWG | Concluded |
| Apr 14 '16 | PRS Meeting | PRS | Concluded |
| Mar 4 '16 | OCITF Meeting | OCITF | Concluded |