NPRR #747 · Revision Request
NPRR747 Revision of Voltage Control Requirements
- PRS Jul 14 '16
- TAC Jul 28 '16
- BOARD Oct 11 '16
- PUCT —
ReasonAddresses current operational issues.
Created2015-12-10
Approved2016-10-11
Sections Affected
2.13.153.15.36.5.7.7
Summary
This Nodal Protocol Revision Request (NPRR) proposes new definitions related to Voltage Profiles, defines various entities’ responsibilities related to Voltage Support, and also clarifies that the interconnecting Transmission Service Provider (TSP) (or its designated agent) may modify a Generation Resource’s Voltage Set Point). This NPRR addresses issues raised at the April 8, 2015 Voltage Workshop.
Timeline
- Nov 25
-
Dec 10
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS Referred → ROS“To table NPRR747 and refer the issue to WMS and ROS.” — Passed→ Language Consideration
- Dec 15
-
Jan 6
Listed without action at 2 meetings (Jan 6 '16 – Jan 7 '16)
- Jan 14
- Jan 26
- Feb 11
- Feb 18
- Mar 2
-
Mar 3
Listed without action at 8 meetings (Mar 3 '16 – Apr 15 '16)
- Apr 22
-
May 4
Listed without action at 6 meetings (May 4 '16 – Jun 8 '16)
- Jun 9
-
Jun 16
PRS PRS MeetingPRSRecommended for Approval Amended by the Apr 21 '16 ERCOT comments“To recommend approval of NPRR747 as amended by the 4/21/16 ERCOT comments” — Passed→ PRS for Impact Analysis review
- Jun 22
-
Jun 23
Listed without action at 2 meetings (Jun 23 '16 – Jul 7 '16)
-
Jul 14
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 6/16/16 PRS Report and Impact Analysis for NPRR747” — Passed→ TAC for consideration
-
Jul 28
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR747 as recommended by PRS in the 7/14/16 PRS Report” — Passed→ Board for consideration
- Aug 9
-
Aug 25
Listed without action at 1 meeting
-
Oct 11
BOARDEmail Vote / Unlisted MeetingBOARDApproved“To approve NPRR747 as recommended by TAC in the 7/28/16 TAC Report with an ERCOT Board action effective date of 8/9/16” — Passed
-
—