NPRR #717 · Revision Request
NPRR717 Clarification of EPS Metering Exception for ERS Generation
- PRS Sep 10 '15
- TAC Sep 24 '15
- BOARD Oct 13 '15
- PUCT —
ReasonMeets Strategic goals, Market efficiencies or enhancements, reduces ambiguity
Created2015-08-13
Approved2015-10-13
Sections Affected
10.2.3
Summary
This Nodal Protocol Revision Request (NPRR) adds language in Section 10.2.3 to exempt generation offering Emergency Response Service (ERS) during the current contract period from the ERCOT-Polled Settlement (EPS) metering requirement and allow the EPS-exempt ERS Generator to export energy to the ERCOT System during equipment testing.
Timeline
-
Jul 10
PRSFiled by Austin Energy
-
Aug 13
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR717 as submitted” — Passed→ PRS for Impact Analysis review
- Aug 19
-
Sep 10
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 8/13/15 PRS Report and Impact Analysis for NPRR717” — Passed→ TAC for consideration
-
Sep 24
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR717 as recommended by PRS in the 9/10/15 PRS Report” — Passed→ Board for consideration
-
Oct 13
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR717 as recommended by TAC in the 9/24/15 TAC Report” — Passed