NPRR #715 · Revision Request
NPRR715 Clarification of Generator Modeling in the Market System
- PRS Oct 15 '15
- TAC Oct 29 '15
- BOARD Dec 8 '15
- PUCT —
ReasonAdministrative. Increases the transparency of generator modeling in the current market systems.
Created2015-07-16
Approved2015-12-08
Sections Affected
2.13.8.24.5.1and 6.5.7.3
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the modeling of Resources and brings the Protocols into better alignment with the current market systems by creating a new defined term, Resource Connectivity Node, and specifying that energy injection is at that node.
Timeline
- Jul 1
-
Jul 8
Listed without action at 1 meeting
-
Jul 16
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR715 and refer the issue to WMS” — Passed→ PRS for consideration
- Aug 5
-
Aug 13
Listed without action at 1 meeting
- Sep 2
-
Sep 10
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR715 as submitted” — Passed→ PRS for Impact Analysis review
- Sep 16
-
Oct 15
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 9/10/15 PRS Report and Impact Analysis for NPRR715” — Passed→ TAC for consideration
-
Oct 29
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR715 as recommended by PRS in the 10/15/15 PRS Report” — Passed→ Board for consideration
-
Dec 8
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR715 as recommended by TAC in the 10/29/15 TAC Report” — Passed
-
—
Posted since the last meeting