ERCOT·WATCH Search ercot.com  ⌕
NPRR #710 · Revision Request

NPRR710  Removal of ORDC Phase 2 Language and Modification to HASL Calculation

Approved sponsor ERCOT posted 2015-05-27 ercot.com
ReasonMarket efficiencies or enhancements
Created2015-06-11
Approved2015-08-11
Sections Affected
2.13.96.5.5.26.5.7.26.7.48.1.18.1.1.18.1.1.28.1.1.2.18.1.1.2.1.68.1.1.2.1.78.1.1.4.28.1.1.4.4and 8.1.1.4.5
Summary
This NPRR removes Operating Reserve Demand Curve (ORDC) Phase 2; changes the High Ancillary Service Limit (HASL) calculation to remove Non-Frequency Responsive Capacity (NFRC) included in a Generation Resource’s High Sustained Limit (HSL), thereby creating the opportunity for an ORDC payment for the NFRC capacity through Ancillary Service imbalance Settlement; and clarifies the HASL definition between use in the Resource limit calculator, Reliability Unit Commitment (RUC) optimization, and the capacity shortfall ratio share.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Jul 16 '15PRS To endorse and forward to TAC the 6/11/15 PRS Report as amended by the 7/8/15 ERCOT comments and as revised by PRS; its accompanying Other Binding Document, Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder, (Attachment 1) as amended by the 7/8/15 ERCOT comments; and the revised Impact Analysis for NPRR710 with a recommended priority of 2015 and a rank of 1360Passed
Documents 11
NameTypePostedClassification
710NPRR-01 Removal of ORDC Phase 2 Language and Modification to HASL Calculation 052715 doc May 27 '15 Revision Request
710NPRR-02 Impact Analysis 052715 doc May 27 '15 Staff Report
710NPRR-03 Attachment 1 Methodology for Implementing ORDC 052715 doc May 27 '15 Revision Request
710NPRR-04 WMS Comments 060415 doc Jun 4 '15 Revision Request Comments
710NPRR-05 Revised Impact Analysis 061015 doc Jun 10 '15 Staff Report
710NPRR-06 PRS Report 061115 doc Jun 15 '15 Committee Report
710NPRR-07 ERCOT Comments 070815 doc Jul 10 '15 Revision Request Comments
710NPRR-08 ERCOT Comments Attachment 1 070815 doc Jul 8 '15 Revision Request Comments
710NPRR-09 PRS Report 071615 doc Jul 20 '15 Committee Report
710NPRR-10 TAC Report 073015 doc Jul 31 '15 Committee Report
710NPRR-11 Board Report 081115 doc Aug 11 '15 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Aug 11 '15 Board of Directors Meeting BOARD Concluded
Jul 30 '15 TAC Meeting TAC Concluded
Jul 16 '15 PRS Meeting PRS Concluded
Jun 17 '15 CWG/MCWG Meeting (CANCELLED) CREDITWG Cancelled
Jun 11 '15 PRS Meeting PRS Concluded
Jun 3 '15 WMS Meeting WMS Concluded