NPRR707 Provision of Transmission System Voltage Telemetry to QSEs
ReasonRegulatory requirements
Created2015-06-11
Sections Affected
3.10.7.5.2
Summary
This Nodal Protocol Revision Request (NPRR) requires ERCOT to provide, upon request, transmission system voltage at each Generation Resource Point of Interconnection (POI) to the transmission system through telemetry via Inter-Control Center Communications Protocol (ICCP). This is necessary for the Generation Resource to comply with the latest version of North American Electric Reliability Corportation (NERC) Standard VAR-002-3, Generator Operation for Maintaining Network Voltage Schedules. Paragraph R2, 2.3, requires generation operators to monitor the voltage at the location specified in their voltage schedule. This data is readily available from ERCOT and provision of this data should not violate any of the provisions of Nodal Protocol Section 1.3, Confidentiality.
Action Log 1 milestones
-
Jun 11
PRSDeferred/Tabled→ Language Consideration
Documents 4
| Name | Type | Posted | Classification |
|---|---|---|---|
| 707NPRR-01 Provision of Transmission System Voltage Telemetry to QSEs 052215 | doc | May 22 '15 | Revision Request |
| 707NPRR-02 ERCOT Comments 060915 | doc | Jun 9 '15 | Revision Request Comments |
| 707NPRR-03 PRS Report 061115 | doc | Jun 15 '15 | Committee Report |
| 707NPRR-04 Request for Withdrawal 090915 | doc | Sep 9 '15 | Revision Request Comments |
Meetings That Took It Up 7
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Oct 5 '15 | Voltage Profile Working Group (VPWG) Meeting | VPWG | Concluded |
| Sep 10 '15 | PRS Meeting | PRS | Concluded |
| Aug 13 '15 | PRS Meeting | PRS | Concluded |
| Jul 21 '15 | NDSWG Meeting | NDSWG | Concluded |
| Jul 16 '15 | PRS Meeting | PRS | Concluded |
| Jul 9 '15 | ROS Meeting | ROS | Concluded |
| Jun 11 '15 | PRS Meeting | PRS | Concluded |