ERCOT·WATCH Search ercot.com  ⌕
NPRR #700 · Revision Request

NPRR700  Utilizing Actual Fuel Costs in Startup Offer Caps

Approved sponsor RCWG posted 2015-04-29 ercot.com
ReasonAddresses current operational issues, Market efficiencies or enhancements
Created2015-05-14
Approved2015-08-11
Sections Affected
2.14.4.9.25.7.1.1
Summary
Just before the implementation of the Nodal Market, it was discovered that the Real-Time revenues earned by a Resource while ramping from breaker close to the Lowest Sustained Limit (LSL) were not included in the calculation of Reliability Unit Commitment (RUC) Make-Whole Payments. To mitigate this problem, it was decided to reduce the Startup Costs in RUC guarantee by an amount that approximates the Real-Time revenues (heat rate proxy “H”) to ensure a balanced equation (total cost versus total revenues). The reduction in Startup Costs affects both Day-Ahead Market (DAM) and RUC procurement given that both use the same cost structure in the calculation of Startup Offer caps, even though reducing Startup Costs in DAM by the heat rate proxy “H” is not desirable since it’s a financial market and generators do not earn additional revenues while ramping to the LSL. This Nodal Protocol Revision Request (NPRR) tries to rectify this problem by incorporating the actual fuel costs into the DAM and RUC procurement process and DAM Make-Whole Payment calculation. However, for RUC Make-Whole Payment calculations the Startup Costs should still be reduced by the heat rate proxy “H” to ensure a balanced equation. If approved, this NPRR should be implemented with NPRR 617, Energy Offer Flexibility.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Jun 11 '15PRS To endorse and forward to TAC the 5/14/15 PRS Report as amended by the 6/4/15 ERCOT comments and Impact Analysis for NPRR700 with a recommended priority of 2015 and rank of 1340.Passed
Documents 8
NameTypePostedClassification
700NPRR-01 Utilizing Actual Fuel Costs in Startup Offer Caps 042915 doc Apr 29 '15 Revision Request
700NPRR-02 WMS Comments 050715 doc May 7 '15 Revision Request Comments
700NPRR-03 PRS Report 051415 doc May 19 '15 Committee Report
700NPRR-04 Impact Analysis 052915 doc May 29 '15 Staff Report
700NPRR-05 ERCOT Comments 060415 doc Jun 4 '15 Revision Request Comments
700NPRR-06 PRS Report 061115 doc Jun 17 '15 Committee Report
700NPRR-07 TAC Report 073015 doc Jul 31 '15 Committee Report
700NPRR-08 Board Report 081115 doc Aug 14 '15 Committee Report
Meetings That Took It Up 9
DateMeetingCommitteeStatus
Aug 27 '15 TAC Meeting TAC Concluded
Aug 11 '15 Board of Directors Meeting BOARD Concluded
Jul 30 '15 TAC Meeting TAC Concluded
Jul 8 '15 WMS Meeting WMS Concluded
Jun 11 '15 PRS Meeting PRS Concluded
Jun 3 '15 WMS Meeting WMS Concluded
May 20 '15 CWG/MCWG Meeting CREDITWG Concluded
May 14 '15 PRS Meeting PRS Concluded
May 6 '15 WMS Meeting WMS Concluded