NPRR #687 · Revision Request

NPRR687  Required Telemetry for Operational Awareness and PDCWG Analysis

Approved sponsor GDF SUEZ Energy Marketing NA posted 2015-03-20 ercot.com
ReasonNPRR527, Required Combined Cycle Telemetry for Operational Awareness and PDCWG Analysis, required the telemetry of NFRC for combined cycle units only. However, as recognized in North American Electric Reliability Corporation (NERC) Reliability Standard, BAL-001-TRE-1, and within Nodal Operating Guide Section 2.2.8, Performance/Disturbance/Compliance Analysis, other generator types may also have power augmentation that is not frequency responsive. ERCOT should have the same operational awareness of this NFRC and the PDCWG should have the clarification for when this power augmentation is to be considered in PFR calculations.
Created2015-04-16
Approved2015-06-09
Sections Affected
2.1 and 6.5.5.2
Summary
This Nodal Protocol Revision Request (NPRR) requires the telemetry of any Non-Frequency Responsive Capacity (NFRC) to ERCOT for operational awareness. This NPRR allows the Performance, Disturbance, Compliance Working Group (PDCWG) to accurately measure the Primary Frequency Response (PFR) of Generation Resources while using ERCOT collected data necessary to analyze each Measurable Event. Revisions to the User Guide, “ERCOT Nodal ICCP Communications Handbook” will be required as a result of this NPRR.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Apr 16 '15PRS To recommend approval of NPRR687 as amended by the 4/14/15 ERCOT commentsPassed
Documents 7
NameTypePostedClassification
687NPRR-01 Required Telemetry for Operational Awareness and PDCWG Analysis 032015 doc Mar 20 '15 Revision Request
687NPRR-02 ERCOT Comments 041415 doc Apr 14 '15 Revision Request Comments
687NPRR-03 PRS Report 041615 doc Apr 20 '15 Committee Report
687NPRR-04 Impact Analysis 050615 doc May 6 '15 Staff Report
687NPRR-05 PRS Report 051415 doc May 19 '15 Committee Report
687NPRR-06 TAC Report 052815 doc May 29 '15 Committee Report
687NPRR-07 Board Report 060915 doc Jun 10 '15 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Jun 9 '15 Board of Directors Meeting BOARD Concluded
May 28 '15 TAC Meeting TAC Concluded
May 14 '15 PRS Meeting PRS Concluded
Apr 22 '15 CWG/MCWG Meeting CREDITWG Concluded
Apr 16 '15 PRS Meeting PRS Concluded