NPRR #663 · Revision Request
NPRR663 Ancillary Service Insufficiency Actions
- PRS Sep 10 '15
- TAC Sep 24 '15
- BOARD Oct 13 '15
- PUCT —
ReasonAddresses current operational issues Market Efficiencies or enhancements
Created2014-11-06
Approved2015-10-13
Sections Affected
4.5.25.2.2.26.5.9.3.3
Summary
This Nodal Protocol Revision Request (NPRR) specifies the actions ERCOT will take to ensure sufficient Ancillary Service capacity exists in the event that ERCOT is unable to procure enough Ancillary Service capacity to meet its Ancillary Service Plan through the Day-Ahead Market (DAM). In summary, Supplementary Ancillary Service Market (SASM) and Houly Reliability Unit Commitement (HRUC) will be used, and in the event that Ancillary Service is still insufficient, Ancillary Service will be assigned to Qualified Scheduling Entities (QSEs) with Generation Resources based on available capacity. ERCOT’s intention is to keep this NPRR specific to ERCOT operational actions, with Settlement and other issues to be addressed in an additional NPRR submitted by Market Participants.
Timeline
- Oct 17
-
Nov 6
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR663 and refer the issue to WMS.” — Passed→ PRS for consideration.
- Dec 3
-
Dec 11
Listed without action at 10 meetings (Dec 11 '14 – May 6 '15)
- May 14
-
Jun 3
Listed without action at 1 meeting
-
Jun 11
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR663 and refer the issue to WMS.” — Passed→ PRS for consideration.
- Jul 8
-
Jul 16
Listed without action at 1 meeting
- Aug 5
-
Aug 13
PRS PRS MeetingPRSRecommended for Approval Amended by the Jul 22 '15 ERCOT comments“To recommend approval of NPRR663 as amended by the 7/22/15 ERCOT comments.” — Passed→ Impact Analysis Consideration
- Aug 19
-
Sep 10
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 8/13/15 PRS Report as revised by PRS with an effective date of upon system implementation of NPRR689 and Impact Analysis for NPRR663.” — Passed→ Revision Request Consideration
-
Sep 24
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR663 as recommended by PRS in the 9/10/15 PRS Report.” — Passed→ Revision Request Consideration
-
Oct 13
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR663 as recommended by TAC in the 9/24/15 TAC Report.” — Passed
-
—