NPRR #623 · Revision Request
NPRR623 Measurement and Evaluation of ERS
ReasonAddresses current operational issues. Administrative Regulatory requirements Other: Clarifies ability of ERCOT to use available data to measure output /contribution of Resources in a configuration not fully anticipated in the Protocols.
Created2014-06-11
Sections Affected
3.14.3.38.1.3.1.28.1.3.1.4
Summary
This Nodal Protocol Revision Request (NPRR) proposes minor technical modification to the Protocols to explicitly account for the possibility that an ERS Load, and the ERS Generation located behind the same Point of Interconnection (POI) to the ERCOT Transmission Grid, can both jointly, or independently, provide ERS services and be evaluated appropriately, regardless of the operating characteristics of the industrial facility and its ERS baseline assignment.
Action Log 1 milestones
-
Jun 11
PRSDeferred/Tabled→ PRS for consideration.
Documents 4
| Name | Type | Posted | Classification |
|---|---|---|---|
| 623NPRR-01 Measurement and Evaluation of ERS 050814 | doc | May 8 '14 | Revision Request |
| 623NPRR-02 ERCOT Comments 051414 | doc | May 14 '14 | Revision Request Comments |
| 623NPRR-03 PRS Report 061114 | doc | Jun 16 '14 | Committee Report |
| 623NPRR-04 Request for Withdrawal 070214 | doc | Jul 2 '14 | Revision Request Comments |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 17 '14 | PRS Meeting | PRS | Concluded |
| Jun 11 '14 | PRS Meeting | PRS | Concluded |
| May 15 '14 | PRS Meeting | PRS | Concluded |