NPRR619  Minimum Quantity for DAM PTP Obligation Bids

Approved sponsor ERCOT posted 2014-04-30 ercot.com
ReasonAddresses operational issues
Created2014-05-15
Approved2014-08-12
Sections Affected
4.4.6.1
Summary
This NPRR adds a one-tenth of one Megawatt (MW) minimum quantity for Point-to-Point (PTP) Obligation bids into the Day-Ahead Market (DAM). ERCOT has observed thousands of zero MW quantity PTP Obligation bids submitted daily, which represent a strain on ERCOT software and systems. This contributed to production issues experienced on February 25, 2014. Since the Protocols explicitly impose minimum bid/offer quantities for DAM Energy Bids and DAM Energy-Only Offers, ERCOT believes it is also appropriate to specify a minimum bid quantity for PTP Obligations. The proposed minimum bid quantity of one-tenth MW is the value of the smallest bid increment that ERCOT’s systems currently accept. The system change associated with this clarification will exclude zero MW bids from the DAM, which will preserve system resources for transactions that can be awarded.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
619NPRR-01 Minimum Quantity for DAM PTP Obligation Bids 043014 doc Apr 30 '14 Revision Request
619NPRR-02 Impact Analysis 043014 doc Apr 30 '14 Staff Report
619NPRR-03 PRS Report 051514 doc May 16 '14 Committee Report
619NPRR-04 PRS Report 061114 doc Jun 13 '14 Committee Report
619NPRR-05 TAC Report 062614 doc Jun 30 '14 Committee Report
619NPRR-06 Board Report 081214 doc Aug 12 '14 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Aug 12 '14 Board of Directors Meeting BOARD Concluded
Jun 26 '14 TAC Meeting TAC Concluded
Jun 11 '14 PRS Meeting PRS Concluded
May 22 '14 Joint CWG/MCWG Meeting CREDITWG Concluded