NPRR #604 · Revision Request
NPRR604 Modification to Submission Timeline for Changes to Emergency Operations and Weatherization Plans
- PRS Jul 17 '14
- TAC Jul 31 '14
- BOARD Aug 12 '14
- PUCT —
ReasonMarket efficiences or enhancements
Created2014-04-10
Approved2014-08-12
Sections Affected
3.21
Summary
This Nodal Protocol Revision Request (NPRR) modifies the requirement that Resource Entities submit any changes to their emergency operations or weatherization plans from 30 days to twice per year. The twice-a-year submission requirement would align the Section 3.21 requirements with Section 22, Attachment K, Declaration of Completion of Generation Resource Weatherization Preparations, which is required to be submitted no later than June 1 and December 1 for the applicable summer and winter operating periods. The revisions proposed in this NPRR are consistent with a proposed amendment before the Public Utility Commission of Texas (PUCT) to P.U.C Subst. R. 25.53, Electric Service Emergency Operations Plans (Project 39160, PUC Rulemaking Proceeding Relating to Electric Service Emergency Operations).
Timeline
- Mar 13
- Apr 10
- May 15
-
Jun 11
PRS PRS MeetingPRSRecommended for Approval Amended by the Apr 9 '14 ERCOT comments“To recommend approval as amended by 4/9/14 ERCOT comments” — Passed→ PRS for Impact Analysis Review
- Jun 18
-
Jul 17
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 6/11/14 PRS Report and Impact Analysis to TAC” — Passed→ TAC for consideration
-
Jul 31
TAC TAC MeetingTACRecommended for Approval“To recommend approval as recommended by PRS in the 7/17/14 PRS Report” — Passed→ ERCOT Board for consideration
-
Aug 12
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR604 as recommended by TAC in the 7/31/14 TAC Report.” — Passed
-
—
Posted since the last meeting