NPRR #590 · Revision Request
NPRR590 Inclusion of WSL in the Default Uplift Invoice Allocation
ReasonMarket efficiencies or enhancements; administrative
Created2014-01-16
Approved2014-04-08
Sections Affected
6.6.3.19.19.1
Summary
This Nodal Protocol Revision Request (NPRR) updates the Default Uplift Invoice allocation process to incorporate Wholesale Storage Load (WSL) volumes in order to equitably distribute costs to the market in case of a market shortfall; and corrects the definition for the variable MEBL.
Action Log 5 milestones
-
Jan 16
PRSDeferred/Tabled→ PRS for consideration.
-
Feb 13
PRSRecommended for Approval→ PRS for Impact Analysis review.
-
Mar 18
PRSRecommended for Approval→ TAC for consideration.
-
Mar 27
TACRecommended for Approval→ ERCOT Board for consideration.
-
Apr 8
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Feb 13 '14 | PRS | To recommend approval of NPRR590 as amended by the 2/12/14 ERCOT comments. | Passed |
| Mar 18 '14 | PRS | To endorse and forward the 2/13/14 PRS Report and revised Impact Analysis for NPRR590 to TAC. | Passed |
Documents 10
| Name | Type | Posted | Classification |
|---|---|---|---|
| 590NPRR-01 Inclusion of WSL in the Default Uplift Invoice Alloca | doc | Dec 31 '13 | Revision Request |
| 590NPRR-02 Impact Analysis 123113 | doc | Dec 31 '13 | Staff Report |
| 590NPRR-03 PRS Report 011614 | doc | Jan 20 '14 | Committee Report |
| 590NPRR-04 ERCOT Comments 021214 | doc | Feb 12 '14 | Revision Request Comments |
| 590NPRR-05 PRS Report 021314 | doc | Feb 17 '14 | Committee Report |
| 590NPRR-06 Revised Impact Analysis 030614 | doc | Mar 6 '14 | Staff Report |
| 590NPRR-07 PRS Report 031814 | doc | Mar 19 '14 | Committee Report |
| 590NPRR-08 ERCOT Comments 032414 | doc | Mar 24 '14 | Revision Request Comments |
| 590NPRR-09 TAC Report 032714 | doc | Mar 28 '14 | Committee Report |
| 590NPRR-10 Board Report 040814 | doc | Apr 11 '14 | Committee Report |
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Apr 8 '14 | Board of Directors Meeting | BOARD | Concluded |
| Mar 27 '14 | TAC Meeting | TAC | Concluded |
| Mar 18 '14 | PRS Meeting | PRS | Concluded |
| Feb 20 '14 | Joint CWG/MCWG Meeting | CREDITWG | Concluded |
| Feb 13 '14 | PRS Meeting | PRS | Concluded |
| Jan 16 '14 | PRS Meeting | PRS | Concluded |