NPRR #565 · Revision Request
NPRR565 Seasonal Generation Notifications
ReasonThe current Protocols require Notification if a seasonally operating Resource Entity plans to return to service on dates other than June 1 or continue operating past September 30. This NPRR proposes that a Resource Entity would only need to provide the 15 day Notification if it intends to begin or suspend its Seasonal Operation Period on a date other than the date designated by the Resource Entity in its Notification of Suspension of Operations. Additional revisions are proposed to correct references to Part III of Section 22, Attachment E, that were not included in NPRR514, Seasonal Generation Resource.
Created2013-09-19
Approved2013-12-10
Sections Affected
3.14.1.23.14.1.9
Summary
This Nodal Protocol Revision Request (NPRR) proposes that a seasonally operating Resource Entity’s 15 day Notification requirement (when returning to service early, or suspending operations later) be based on the Seasonal Operation Period designated by the Resource Entity in its Notification of Suspension of Operations. Additional revisions correct references to Part III of Section 22, Attachment E, Notification of Suspension of Operations.
Action Log 4 milestones
-
Sep 19
PRSRecommended for Approval→ PRS for Impact Analysis review.
-
Oct 17
PRSRecommended for Approval→ TAC for consideration.
-
Nov 7
TACRecommended for Approval→ ERCOT Board for consideration.
-
Dec 10
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 565NPRR-01 Seasonal Generation Notifications 082313 | doc | Aug 23 '13 | Revision Request |
| 565NPRR-02 PRS Report 091913 | doc | Sep 24 '13 | Committee Report |
| 565NPRR-03 Impact Analysis 100913 | doc | Oct 9 '13 | Staff Report |
| 565NPRR-04 PRS Report 101713 | doc | Oct 22 '13 | Committee Report |
| 565NPRR-05 TAC Report 110713 | doc | Nov 8 '13 | Committee Report |
| 565NPRR-06 Board Report 121013 | doc | Dec 10 '13 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 10 '13 | Board of Directors Meeting | BOARD | Concluded |
| Nov 7 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Oct 17 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Sep 25 '13 | Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting | CREDITWG | Concluded |
| Sep 19 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |