NPRR561  Clarification of Shutdown Telemetry Status

Approved sponsor ERCOT posted 2013-08-09 ercot.com
  1. PRS Oct 17 '13
  2. TAC Nov 7 '13
  3. BOARD Dec 10 '13
  4. PUCT
ReasonThe language in Protocol Section 3.9.1 is inconsistent with the Business Practice Manual "ERCOT and QSE Operations Practices During the Operating Hour", Section 3.3, Generation Resource Shutdown.
Created2013-09-19
Approved2013-12-10
Sections Affected
3.9.1
Summary
This Nodal Protocol Revision Request (NPRR) revises Section 3.9.1 to clarify that Generation Resources that are providing Non-Spinning Reserve (Non-Spin) and that can continue to be available for deployment within the time frame established in the Protocols, may continue to carry Off-Line Non-Spin during shutdown.