NPRR #546 · Revision Request
NPRR546 Removal of References to RUC Notifications
ReasonNPRR207, Unit Deselection, approved by the ERCOT Board on 7/20/10, introduced the term "RUC Notification" into the Protocols. A RUC Notification is a notification that would be sent out by ERCOT to a Qualified Scheduling Entity (QSE) when a RUC process recommended the QSE’s Resource, but ERCOT Operators opted to deselect the Resource for commitment. The language requiring ERCOT to send out this notification to the individual QSE was later replaced with a requirement for an aggregate report. This was done as part of NPRR321 during discussion at the 6/23/11 PRS meeting.
Created2013-06-20
Approved2013-11-19
Sections Affected
2.14.4.9.2.15.5.2
Summary
This Nodal Protocol Revision Request (NPRR) removes outstanding references to "Reliability Unit Commitment (RUC) Notifications." This language is no longer relevant as a result of changes made through NPRR321, Allow Change to Energy Offer Curve MW Amounts in the Adjustment Period, which was approved by the ERCOT Board on 9/20/11.
Action Log 4 milestones
-
Jun 20
PRSRecommended for Approval→ PRS Impact Analysis review
-
Jul 18
PRSRecommended for Approval→ TAC consideration of NPRR546
-
Sep 5
TACRecommended for Approval→ ERCOT Board consideration of NPRR546
-
Nov 19
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 546NPRR-01 Removal of References to RUC Notifications 060413 | doc | Jun 4 '13 | Revision Request |
| 546NPRR-02 Impact Analysis 060413 | doc | Jun 4 '13 | Staff Report |
| 546NPRR-03 PRS Report 062013 | doc | Jun 25 '13 | Committee Report |
| 546NPRR-04 PRS Report 071813 | doc | Jul 22 '13 | Committee Report |
| 546NPRR-05 TAC Report 090513 | doc | Sep 5 '13 | Committee Report |
| 546NPRR-06 Board Report 111913 | doc | Nov 19 '13 | Committee Report |
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Nov 19 '13 | Board of Directors Meeting | BOARD | Concluded |
| Sep 5 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Jul 18 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Jun 26 '13 | Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting | CREDITWG | Concluded |
| Jun 20 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Jun 12 '13 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |