NPRR531  Clarification of IRR Forecasting Process Posting Requirement

Approved sponsor ERCOT posted 2013-03-22 ercot.com
ReasonThe requirement for ERCOT to publish procedures describing the forecasting process was added to Section 3.2.1 by NPRR230, Resolution of Alignment Items A40, A108, A127 and A138 and Clarification/Updates to Load and Demand Forecast, Statement of Opportunities, and Long Term Wind Power Forecast. While the intent of this requirement was for ERCOT to publish its wind or IRR forecasting procedures, paragraph (5) of Section 3.2.1 does not specify that the requirement is specific to wind or IRR forecasting. This NPRR removes any ambiguity regarding the forecasting process posting requirement.
Created2013-04-18
Approved2013-07-16
Sections Affected
3.2.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that the procedures describing the forecasting process that ERCOT must publish on the Market Information System (MIS) Public Area pursuant to Section 3.2.1 relate specifically to ERCOT's Intermittent Renewable Resource (IRR) forecasting process.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
531NPRR-01 Clarification of IRR Forecasting Process Posting Requ doc Mar 22 '13 Revision Request
531NPRR-02 Impact Analysis 032213 doc Mar 22 '13 Staff Report
531NPRR-03 PRS Report 041813 doc Apr 22 '13 Committee Report
531NPRR-04 PRS Report 051613 doc May 20 '13 Committee Report
531NPRR-05 TAC Report 060613 doc Jun 6 '13 Committee Report
531NPRR-06 Board Report 071613 doc Jul 17 '13 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Jul 16 '13 Board of Directors Meeting BOARD Concluded
Jun 6 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
May 16 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 24 '13 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting CREDITWG Concluded
Apr 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded