NPRR #531 · Revision Request
NPRR531 Clarification of IRR Forecasting Process Posting Requirement
- PRS May 16 '13
- TAC Jun 6 '13
- BOARD Jul 16 '13
- PUCT —
ReasonThe requirement for ERCOT to publish procedures describing the forecasting process was added to Section 3.2.1 by NPRR230, Resolution of Alignment Items A40, A108, A127 and A138 and Clarification/Updates to Load and Demand Forecast, Statement of Opportunities, and Long Term Wind Power Forecast. While the intent of this requirement was for ERCOT to publish its wind or IRR forecasting procedures, paragraph (5) of Section 3.2.1 does not specify that the requirement is specific to wind or IRR forecasting. This NPRR removes any ambiguity regarding the forecasting process posting requirement.
Created2013-04-18
Approved2013-07-16
Sections Affected
3.2.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that the procedures describing the forecasting process that ERCOT must publish on the Market Information System (MIS) Public Area pursuant to Section 3.2.1 relate specifically to ERCOT's Intermittent Renewable Resource (IRR) forecasting process.
Timeline
- Mar 22
-
Apr 18
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval“To recommend approval of NPRR531 as submitted.” — Passed→ PRS Impact Analysis review
- Apr 24
-
May 16
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 4/18/13 PRS Report and Impact Analysis for NPRR531 to TAC.” — Passed→ TAC consideration of NPRR531
-
Jun 6
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval“To recommend approval of NPRR531 as recommended by PRS in the 5/16/13 PRS Report.” — Passed→ ERCOT Board consideration of NPRR531
-
Jul 16
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR531 as recommended by TAC in the 6/6/13 TAC Report.” — Passed
-
—