NPRR #522 · Revision Request
NPRR522 Adjustment of Demand Response Performance for Distribution Losses (formerly "Adjustment of Demand Response Performance for T&D Losses ")
- PRS May 16 '13
- TAC Jun 6 '13
- BOARD Jul 16 '13
- PUCT —
ReasonThis NPRR would adjust the quantity of demand response that can be offered into Ancillary Services and Emergency Response Services (ERS) to include an adjustment for line losses.
Created2013-03-21
Approved2013-07-16
Sections Affected
3.7.1.23.9.13.14.3.34.4.7.2.18.1.1.213.3
Summary
This Nodal Protocol Revision Request (NPRR) addresses inequality by adjusting the metered Load of demand response Resources for Distribution Losses.
Timeline
- Feb 25
-
Mar 8
Listed without action at 2 meetings (Mar 8 '13 – Mar 13 '13)
-
Mar 21
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Amended by the Mar 14 '13 DSWG comments Amended by the PRS comments“To recommend approval of NPRR522 as amended by the 3/14/13 DSWG comments and as revised by PRS” — Passed→ PRS IA Review
- Mar 27
- Apr 12
-
Apr 18
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Amended by the Apr 18 '13 CPS Energy comments“To recommend approval of NPRR522 as amended by the 4/18/13 CPS Energy comments and as revised by PRS” — Passed→ PRS IA Review
-
May 16
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 4/18/13 PRS Report and Impact Analysis for NPRR522 to TAC” — Passed
-
Jun 6
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval“To recommend approval of NPRR522 as recommended by PRS in the 5/16/13 PRS Report” — Passed→ ERCOT Board Consideration
-
Jul 16
BOARD Board of Directors MeetingBOARDApproved“To approve NRR522 as recommended by TAC in the 6/6/13 TAC Report” — Passed
-
—
Posted since the last meeting