NPRR516  Change to Verifiable Cost Manual Revision Process

Approved sponsor ERCOT posted 2013-02-06 ercot.com
ReasonThe current Verifiable Cost Manual change control process requires that ERCOT post approved changes to the ERCOT website within one Business Day after approval and lacks sufficient detail regarding effective dates and assessment of impacts to ERCOT. As is the case with the ERCOT Protocols and market guides, a revision to the Verifiable Cost Manual may require ERCOT to modify its systems or business practices. Information regarding impacts should be available for consideration by stakeholders when reviewing any revision request. Accordingly, ERCOT proposes that the common ERCOT Protocol and market guide change control process be adopted for the Verifiable Cost Manual. This change control process is familiar to stakeholders, is appropriately detailed, and provides a more reasonable review and posting timeline.
Created2013-02-21
Approved2013-07-16
Sections Affected
5.6.1
Summary
This Nodal Protocol Revision Request (NPRR) removes the Verifiable Cost Manual revision process from Section 5.6.1. In conjunction with this revision, the Verifiable Cost Manual was revised to incorporate a change control process analogous to the common process used in ERCOT Protocols and market guides.
Action Log 4 milestones
Documents 7
NameTypePostedClassification
516NPRR-01 Change to Verifiable Cost Manual Revision Process 020 doc Feb 6 '13 Revision Request
516NPRR-02 Impact Analysis 020613 doc Feb 6 '13 Staff Report
516NPRR-03 WMS Comments 021513 doc Feb 15 '13 Revision Request Comments
516NPRR-04 PRS Report 022113 doc Feb 25 '13 Committee Report
516NPRR-05 PRS Report 032113 doc Mar 25 '13 Committee Report
516NPRR-06 TAC Report 050213 doc May 6 '13 Committee Report
516NPRR-07 Board Report 071613 doc Jul 17 '13 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Jul 16 '13 Board of Directors Meeting BOARD Concluded
May 2 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Mar 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 27 '13 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting CREDITWG Concluded
Feb 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded