ERCOT·WATCH Search ercot.com  ⌕
NPRR #515 · Revision Request

NPRR515  Day-Ahead Market Self-Commitment of Generation Resources

Approved sponsor ERCOT posted 2013-02-05 ercot.com
ReasonThere currently exists a mechanism for Generation Resources to self-commit and allow the DAM to optimize their energy and Ancillary Service offers. The effect of the self-commitment is to nullify the temporal constraints as well as the requirement to award a block at Low Sustained Limit (LSL). However, the implementation of this is such that it is restricted to a daily decision (self-committed or not for the entire set of hours for that day). Implementation of this NPRR would essentially create an hour-by-hour self-commitment flag.
Created2013-02-21
Approved2013-07-16
Sections Affected
4.4.9.14.5.1
Summary
This Nodal Protocol Revision Request (NPRR) adds a Day-Ahead Market (DAM) mechanism for self-committing Generation Resources on an hourly basis; and makes a minor clarification to the description of the timing of the Simultaneous Feasibility Test (SFT) process.
Action Log 5 milestones
Documents 10
NameTypePostedClassification
515NPRR-01 Day-Ahead Market Self-Commitment of Generation Resour doc Feb 5 '13 Revision Request
515NPRR-02 Impact Analysis 020513 doc Feb 5 '13 Staff Report
515NPRR-03 PRS Report 022113 doc May 21 '13 Committee Report
515NPRR-04 WMS Comments 031413 doc Mar 14 '13 Revision Request Comments
515NPRR-05 ERCOT Comments 040413 doc Apr 4 '13 Revision Request Comments
515NPRR-06 WMS Comments 041513 doc Apr 15 '13 Revision Request Comments
515NPRR-07 PRS Report 041813 doc May 21 '13 Committee Report
515NPRR-08 PRS Report 051613 doc May 21 '13 Committee Report
515NPRR-09 TAC Report 060613 doc Jun 6 '13 Committee Report
515NPRR-10 Board Report 071613 doc Jul 17 '13 Committee Report
Meetings That Took It Up 18
DateMeetingCommitteeStatus
Jun 14 '16 Board of Directors Meeting BOARD Concluded
May 26 '16 TAC Meeting TAC Concluded
May 25 '16 WebEx Workshop: Review of Operational Impact of NPRR515 Concluded
May 12 '16 PRS Meeting PRS Concluded
Apr 14 '16 PRS Meeting PRS Concluded
Jul 8 '15 WMS Meeting WMS Concluded
Jun 3 '15 WMS Meeting WMS Concluded
Jul 16 '13 Board of Directors Meeting BOARD Concluded
Jun 6 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
May 16 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 24 '13 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting CREDITWG Concluded
Apr 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 12 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Apr 3 '13 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Mar 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Mar 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Mar 12 '13 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Feb 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded