NPRR #513 · Revision Request
NPRR513 Removal of Nodal Implementation Surcharge
ReasonSince October 1, 2006, ERCOT has been assessing an NIS, most recently $0.375 per MWh of generation, to fund implementation of the Nodal market. ERCOT achieved full recovery of these costs with the Initial Settlement of Operating Day January 1, 2013. The NIS was discontinued with the Settlement of Operating Day January 2, 2013.
Created2013-02-21
Approved2013-07-16
Sections Affected
2.23.14.1.103.14.1.135.6.15.6.1.15.6.1.29.5.39.16.4
Summary
This Nodal Protocol Revision Request (NPRR) removes references to the Nodal Implementation Surcharge (NIS).
Action Log 4 milestones
-
Feb 21
PRSRecommended for Approval→ PRS Impact Analysis Review
-
Mar 21
PRSRecommended for Approval→ TAC Consideration
-
May 2
TACRecommended for Approval→ ERCOT Board Consideration
-
Jul 16
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 513NPRR-01 Removal of Nodal Implementation Surcharge 013013 | doc | Jan 30 '13 | Revision Request |
| 513NPRR-02 Impact Analysis 013013 | doc | Jan 30 '13 | Staff Report |
| 513NPRR-03 PRS Report 022113 | doc | Feb 22 '13 | Committee Report |
| 513NPRR-04 PRS Report 032113 | doc | Mar 25 '13 | Committee Report |
| 513NPRR-05 TAC Report 050213 | doc | May 7 '13 | Committee Report |
| 513NPRR-06 Board Report 071613 | doc | Jul 17 '13 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 16 '13 | Board of Directors Meeting | BOARD | Concluded |
| May 2 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Mar 21 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Feb 27 '13 | Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting | CREDITWG | Concluded |
| Feb 21 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |