NPRR #505 · Revision Request

NPRR505  ERS Weather-Sensitive Loads

Withdrawn sponsor ERCOT posted 2012-11-28 ercot.com
ReasonERS is procured for four-month Contract Terms and requires participating Loads to meet availability and performance requirements for a fixed capacity obligation for the entire term. This has limited the ability of weather-sensitive Loads to offer their full potential and/or to meet event or test performance requirements during periods of mild weather. Consequently, ERS in its five-year history has attracted very little participation from weather-sensitive Loads. Peak demand in the ERCOT Region, both in summer and winter, is driven by weather-sensitive Load, primarily residential and small commercial air conditioning in the summer and electric heat in winter. This NPRR is expected to make ERS more accessible for HVAC-driven Loads, in turn enhancing grid reliability by attracting more emergency demand response capacity to ERS.
Created2012-12-13
Sections Affected
2.13.14.3.5 (new)6.6.11.16.6.11.28.1.3.1.5 (new)8.1.3.1.5.1 (new)8.1.3.1.5.2 (new)8.1.3.1.5.4 (new)8.1.3.1.5.4 (new)8.1.3.1.5.5 (new)8.1.3.3.1
Summary
This Nodal Protocol Revision Request (NPRR) establishes rules for participation in Emergency Response Service (ERS) by Loads with demand response capability that is highly sensitive to weather conditions. It creates a new category of ERS Resource — ERS Weather-Sensitive Load — and provides for their participation in ERS under the following conditions: · ERS Weather-Sensitive Loads would be eligible to participate as ERS Weather-Sensitive Loads only during ERS Time Periods that correlate to peak weather conditions (e.g., Business Hours 2 and Business Hours 3 during the June-September Standard Contract Term). · Qualified Scheduling Entities (QSEs) representing ERS Weather-Sensitive Loads would be compensated for those Resources based solely on their performance during deployment events and during unannounced testing. · Because ERCOT expects this category of Resource to consist primarily of aggregations of small customer Loads which may be subject to growth and/or churn, QSEs representing ERS Weather-Sensitive Loads would be allowed to adjust the population of their aggregations on a monthly basis during an ERS Standard Contract Term. · The NPRR establishes a structure of payment reductions for QSEs to protect against over-stated offers or projected program growth. · ERS Weather-Sensitive Loads would be subject to a maximum of eight deployment events of up to three hours per event during an ERS Contract Period. In addition, ERS Weather-Sensitive Loads are subject to up to eight ERCOT-administered unannounced tests per ERS Standard Contract Term.
Action Log 5 milestones
Ballots
DateBodyResultYesNoAbstain
WMS Motion Carries 4.5 2 11 xls
Documents 21
NameTypePostedClassification
505NPRR-01 ERS Weather-Sensitive Loads 112812 doc Nov 28 '12 Revision Request
505NPRR-02 Preliminary Impact Analysis 112812 doc Nov 28 '12 Staff Report
505NPRR-03 TXU Energy Comments 121212 doc Dec 12 '12 Revision Request Comments
505NPRR-04 Luminant Energy Company LLC Comments 121212 doc Dec 12 '12 Revision Request Comments
505NPRR-05 ERCOT Comments 121212 doc Dec 12 '12 Revision Request Comments
505NPRR-06 PRS Report 121312 doc Dec 18 '12 Committee Report
505NPRR-07 WMS Comments 011013 doc Jan 10 '13 Revision Request Comments
505NPRR-08 WMS Roll Call Vote 011013 xls Jan 10 '13 Revision Request Ballot
505NPRR-09 ROS Comments 011513 doc Jan 15 '13 Revision Request Comments
505NPRR-10 Citigroup Energy Inc Comments 011613 doc Jan 16 '13 Revision Request Comments
505NPRR-11 PRS Report 011713 doc Jan 21 '13 Committee Report
505NPRR-12 ERCOT Appeal 013113 doc Jan 31 '13 Legal filings and governance
505NPRR-13 PRS Advocate Comments 020513 doc Feb 5 '13 Revision Request Comments
505NPRR-14 DR Coalition Comments 020613 doc Feb 6 '13 Revision Request Comments
505NPRR-15 PUCT Staff Comments 020613 doc Feb 6 '13 Revision Request Comments
505NPRR-16 Sierra Club Comments 020713 doc Feb 7 '13 Revision Request Comments
505NPRR-17 TAC Report 020713 doc Feb 8 '13 Committee Report
505NPRR-18 DR Coalition Comments 022013 doc Feb 20 '13 Revision Request Comments
505NPRR-19 ERCOT Comments 022013 doc Feb 20 '13 Revision Request Comments
505NPRR-20 PRS Report 022113 doc Feb 25 '13 Committee Report
505NPRR-21 Request for Withdrawal 100213 doc Oct 2 '13 Revision Request Comments
Meetings That Took It Up 17
DateMeetingCommitteeStatus
Oct 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Sep 19 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 22 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 20 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
May 16 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Mar 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 7 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Jan 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jan 10 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Jan 9 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Dec 14 '12 Commercial Operations Subcommittee (COPS) Meeting COPS Concluded
Dec 13 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 6 '12 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Dec 5 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded