NPRR #502 · Revision Request

NPRR502  Addition of Year 6 to the SSWG Base Cases

Approved sponsor Planning Working Group (PLWG) posted 2012-11-20 ercot.com
ReasonThe present bases cases (Data Set B) cover a planning period of five years. This timeframe is not sufficient to address large regional projects with scopes requiring long-lead time consideration (i.e., 345-kV and certification). In many cases, the entire project spectrum including initial assessments, identification of alternatives, project selection, certification, and implementation takes longer than five years. Additionally, near-term economic projects potentially having reliability drivers beyond the five-year planning horizon can be supported with this additional base case. Similarly, this additional Year 6 base case can help provide direction to the selection of a longer term solution potentially resulting in a more cost-effective near-term plan development. Lastly, proposed North American Electric Reliability Corporation (NERC) Reliability Standard TPL-001-2, Transmission System Planning Performance Requirements, requires assessment for one of the years in the "Long-Term Transmission Planning Horizon (years 6-10)."
Created2012-12-13
Approved2013-03-19
Sections Affected
3.10.23.11.4.1
Summary
This Nodal Protocol Revision Request (NPRR) adds a sixth year (Year 6) to the Steady State Working Group (SSWG) Data Set B base cases. Revisions to the Transmission Project and Information Tracking (TPIT) and Annual Load Data Request (ALDR) procedures will be required as result of this NPRR. The Planning Working Group (PLWG) has submitted Planning Guide Revision Request (PGRR) 026, Addition of Year 6 to the SSWG Base Cases, to revise related sections of the Planning Guide.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Jan 17 '13PRS To endorse and forward the 12/13/12 PRS Report and revised Impact Analysis for NPRR502 to TACPassed
Documents 7
NameTypePostedClassification
502NPRR-01 Addition of Year 6 to the SSWG Base Cases 112012 doc Nov 20 '12 Revision Request
502NPRR-02 PRS Report 121312 doc Dec 18 '12 Committee Report
502NPRR-03 Impact Analysis 010213 doc Jan 2 '13 Staff Report
502NPRR-04 Revised Impact Analysis 010913 doc Jan 9 '13 Staff Report
502NPRR-05 PRS Report 011713 doc Jan 21 '13 Committee Report
502NPRR-06 TAC Report 020713 doc Feb 8 '13 Committee Report
502NPRR-07 Board Report 031913 doc Mar 22 '13 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Mar 19 '13 Board of Directors Meeting BOARD Concluded
Feb 7 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Jan 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 13 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 4 '12 Planning Working Group (PLWG) Meeting PLWG Concluded